DR-1501 · Puerto Rico
Project worksheets 3–367
SEVERE STORMS, FLOODING, MUDSLIDES, AND LANDSLIDES
Showing 1–100 of 158 worksheets with dated revisions, in worksheet number order.
Worksheet timelines
Jump to a worksheet number range
- 3–367
- 368–610
| Worksheet | Applicant location | Work category | Last activity date | Last signed change | Federal share in project snapshot |
|---|---|---|---|---|---|
| 3 | Unavailable | Emergency Protective Measures | March 30, 2004 | $6,352.50 | $36,472.50 |
| 27 | Unavailable | Roads and Bridges | December 17, 2007 | -$3,046.35 | $39,656.25 |
| 37 | Unavailable | Roads and Bridges | June 20, 2007 | -$6,013.13 | $39,778.57 |
| 41 | Unavailable | Roads and Bridges | May 24, 2004 | -$789.68 | $6,904.65 |
| 47 | Unavailable | Roads and Bridges | October 29, 2010 | -$7,197.83 | $0.00 |
| 52 | Unavailable | Roads and Bridges | October 29, 2010 | -$4,653.60 | $0.00 |
| 57 | Unavailable | Roads and Bridges | December 11, 2006 | -$22.50 | $0.00 |
| 59 | Unavailable | Roads and Bridges | October 29, 2010 | -$10,180.99 | $0.00 |
| 60 | Unavailable | Roads and Bridges | October 29, 2010 | -$71,373.15 | $0.00 |
| 63 | Unavailable | Roads and Bridges | May 22, 2012 | -$14,304.75 | $15,082.88 |
| 67 | Unavailable | Roads and Bridges | February 5, 2004 | -$29,873.40 | $11,113.35 |
| 68 | Unavailable | Roads and Bridges | February 5, 2004 | -$18,204.00 | $17,267.74 |
| 72 | Unavailable | Roads and Bridges | May 11, 2009 | -$348.00 | $13,165.73 |
| 74 | Unavailable | Roads and Bridges | May 4, 2004 | $3,327.11 | $10,900.27 |
| 75 | Unavailable | Roads and Bridges | February 17, 2004 | -$9,526.10 | $0.00 |
| 76 | Unavailable | Roads and Bridges | June 1, 2004 | $4,309.50 | $4,309.50 |
| 78 | Unavailable | Roads and Bridges | May 4, 2004 | $3,074.80 | $33,352.26 |
| 83 | Unavailable | Roads and Bridges | October 16, 2007 | -$15,165.86 | $54,006.30 |
| 86 | Unavailable | Roads and Bridges | August 11, 2008 | $19,451.25 | $19,451.25 |
| 91 | Unavailable | Roads and Bridges | April 20, 2004 | $7,758.00 | $10,734.60 |
| 101 | Unavailable | Roads and Bridges | April 10, 2007 | -$9,094.80 | $0.00 |
| 105 | Unavailable | Roads and Bridges | July 27, 2007 | -$587.63 | $2,559.90 |
| 111 | Unavailable | Roads and Bridges | July 27, 2007 | $2,053.31 | $5,878.91 |
| 126 | Unavailable | Roads and Bridges | March 12, 2008 | -$2,314.73 | $0.00 |
| 134 | Unavailable | Roads and Bridges | July 27, 2007 | $717.75 | $3,501.15 |
| 135 | Unavailable | Roads and Bridges | October 29, 2010 | -$6,916.55 | $14,711.01 |
| 136 | Unavailable | Roads and Bridges | August 11, 2008 | -$4,764.23 | $0.00 |
| 139 | Unavailable | Roads and Bridges | July 27, 2007 | -$5,877.75 | $2,776.09 |
| 152 | Unavailable | Roads and Bridges | June 3, 2004 | -$8,179.25 | $0.00 |
| 153 | Unavailable | Roads and Bridges | June 3, 2004 | -$14,704.46 | $0.00 |
| 154 | Unavailable | Roads and Bridges | July 15, 2004 | $81,179.74 | $134,132.70 |
| 156 | Unavailable | Roads and Bridges | July 27, 2007 | $2,497.50 | $10,271.57 |
| 157 | Unavailable | Roads and Bridges | December 17, 2007 | -$6,155.93 | $0.00 |
| 169 | Unavailable | Roads and Bridges | October 29, 2010 | -$98,441.14 | $0.00 |
| 172 | Unavailable | Roads and Bridges | October 29, 2010 | -$40,764.94 | $0.00 |
| 177 | Unavailable | Roads and Bridges | October 29, 2010 | -$34,091.36 | $0.00 |
| 180 | Unavailable | Roads and Bridges | January 23, 2004 | -$4,941.80 | $0.00 |
| 182 | Unavailable | Roads and Bridges | July 15, 2004 | $1,043.64 | $4,422.02 |
| 187 | Unavailable | Roads and Bridges | June 15, 2004 | $6,373.13 | $10,715.32 |
| 190 | Unavailable | Roads and Bridges | August 11, 2008 | -$21,168.23 | $34,723.27 |
| 192 | Statewide | Emergency Protective Measures | August 10, 2007 | -$372.15 | $201,425.09 |
| 193 | Statewide | Emergency Protective Measures | February 17, 2004 | $4,910.12 | $23,180.31 |
| 194 | Unavailable | Roads and Bridges | July 27, 2007 | $620.25 | $5,006.74 |
| 206 | Unavailable | Roads and Bridges | December 11, 2006 | -$28,983.69 | $14,107.71 |
| 208 | Unavailable | Roads and Bridges | May 12, 2004 | $716.25 | $3,410.63 |
| 209 | Unavailable | Roads and Bridges | August 11, 2008 | -$4,245.75 | $0.00 |
| 211 | Unavailable | Roads and Bridges | May 12, 2004 | $3,660.94 | $5,453.78 |
| 213 | Unavailable | Roads and Bridges | August 11, 2008 | -$8,625.00 | $0.00 |
| 216 | Unavailable | Roads and Bridges | October 27, 2006 | $3,806.25 | $8,044.20 |
| 219 | Unavailable | Roads and Bridges | October 27, 2006 | $2,439.38 | $4,896.01 |
| 221 | Unavailable | Roads and Bridges | October 27, 2006 | $1,125.00 | $6,806.25 |
| 223 | Unavailable | Roads and Bridges | October 27, 2006 | $10,244.25 | $13,731.45 |
| 224 | Unavailable | Roads and Bridges | July 15, 2004 | $1,406.25 | $2,221.88 |
| 234 | Unavailable | Roads and Bridges | September 2, 2004 | $1,659.00 | $37,663.76 |
| 237 | Unavailable | Roads and Bridges | February 7, 2007 | -$9,885.44 | $40,002.18 |
| 239 | Unavailable | Roads and Bridges | July 15, 2004 | $4,050.00 | $10,249.20 |
| 242 | Unavailable | Roads and Bridges | May 5, 2005 | $2,740.43 | $2,740.43 |
| 243 | Unavailable | Roads and Bridges | March 12, 2008 | -$6,885.38 | $0.00 |
| 245 | Unavailable | Roads and Bridges | July 15, 2004 | $962.66 | $2,038.15 |
| 247 | Unavailable | Roads and Bridges | May 4, 2004 | $624.75 | $1,844.25 |
| 250 | Unavailable | Roads and Bridges | December 11, 2006 | -$1,109.25 | $1,977.90 |
| 251 | Unavailable | Roads and Bridges | March 12, 2008 | -$25,396.73 | $0.00 |
| 257 | Unavailable | Roads and Bridges | April 19, 2004 | $8,607.38 | $24,645.41 |
| 258 | Unavailable | Roads and Bridges | July 15, 2004 | $8,319.45 | $9,071.66 |
| 259 | Unavailable | Roads and Bridges | July 15, 2004 | $6,468.75 | $32,897.57 |
| 260 | Unavailable | Roads and Bridges | August 20, 2004 | $962.66 | $8,716.42 |
| 262 | Unavailable | Roads and Bridges | July 15, 2004 | $12,750.00 | $13,723.88 |
| 264 | Unavailable | Roads and Bridges | July 15, 2004 | $3,300.00 | $5,549.93 |
| 270 | Unavailable | Roads and Bridges | August 11, 2008 | -$37,526.44 | $0.00 |
| 273 | Unavailable | Roads and Bridges | February 7, 2007 | -$28,572.51 | $67,747.13 |
| 275 | Unavailable | Roads and Bridges | July 15, 2004 | $132.00 | $1,258.73 |
| 276 | Unavailable | Roads and Bridges | July 15, 2004 | $2,030.03 | $3,297.96 |
| 277 | Unavailable | Roads and Bridges | May 12, 2004 | $1,912.50 | $15,454.61 |
| 278 | Unavailable | Roads and Bridges | August 11, 2008 | -$3,159.49 | $0.00 |
| 288 | Unavailable | Roads and Bridges | August 11, 2008 | -$4,854.79 | $0.00 |
| 290 | Unavailable | Roads and Bridges | July 15, 2004 | $14,246.25 | $40,262.21 |
| 294 | Unavailable | Roads and Bridges | June 21, 2004 | $2,129.48 | $4,472.10 |
| 295 | Unavailable | Roads and Bridges | August 18, 2009 | -$8,423.23 | $35,475.00 |
| 296 | Unavailable | Roads and Bridges | August 11, 2008 | -$27,059.56 | $55,847.81 |
| 299 | Unavailable | Roads and Bridges | November 30, 2004 | $10,130.25 | $21,057.37 |
| 302 | Unavailable | Roads and Bridges | July 15, 2004 | $1,933.58 | $3,710.59 |
| 303 | Unavailable | Roads and Bridges | July 15, 2004 | $3,132.90 | $6,392.46 |
| 304 | Unavailable | Roads and Bridges | June 15, 2004 | $1,452.00 | $1,452.00 |
| 307 | Unavailable | Roads and Bridges | June 15, 2004 | $2,112.00 | $2,112.00 |
| 311 | Unavailable | Roads and Bridges | August 11, 2008 | -$12,510.74 | $30,605.82 |
| 319 | Unavailable | Roads and Bridges | August 9, 2004 | $10,395.68 | $11,736.27 |
| 323 | Unavailable | Roads and Bridges | July 26, 2004 | $10,215.75 | $15,971.00 |
| 331 | Unavailable | Debris Removal | October 25, 2006 | -$187.50 | $79,158.00 |
| 336 | Unavailable | Roads and Bridges | December 17, 2007 | -$8,081.78 | $0.00 |
| 347 | Unavailable | Roads and Bridges | December 17, 2007 | -$8,834.22 | $38,156.01 |
| 349 | Unavailable | Roads and Bridges | May 11, 2009 | -$16,970.00 | $55,708.42 |
| 351 | Unavailable | Emergency Protective Measures | May 24, 2004 | $16,138.30 | $30,070.54 |
| 353 | Statewide | Roads and Bridges | April 30, 2013 | -$6,056.13 | $3,360.70 |
| 356 | Statewide | Roads and Bridges | April 30, 2013 | -$5,962.50 | $0.00 |
| 358 | Statewide | Roads and Bridges | May 24, 2004 | $1,821.84 | $2,908.01 |
| 359 | Statewide | Roads and Bridges | May 14, 2004 | $9,002.95 | $10,217.89 |
| 360 | Unavailable | Emergency Protective Measures | May 24, 2004 | $2,911.38 | $24,669.72 |
| 363 | Unavailable | Roads and Bridges | December 17, 2007 | -$22.50 | $54,889.50 |
| 364 | Unavailable | Roads and Bridges | December 17, 2007 | -$21,972.00 | $37,558.28 |
| 367 | Unavailable | Roads and Bridges | August 11, 2008 | -$20,520.60 | $22,374.75 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity