DR-1543 · South Carolina
HURRICANE CHARLEY
Hurricane · Declared September 1, 2004
Recorded incident start August 14, 2004. Recorded incident end August 15, 2004. Declaration request August 20, 2004. Recorded closeout September 27, 2013.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Georgetown County, South Carolina | Public Assistance · Hazard Mitigation | Unavailable |
| Horry County, South Carolina | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 97
- Federal share obligated
- $2,317,127.17
- Median days to first recorded obligation
- 57
Timing uses 97 dated worksheets and starts on the original declaration date. Earliest first obligation September 28, 2004. Most recent obligation in the project snapshot June 21, 2013.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 11 | $897,161.78 |
| Debris Removal | 22 | $661,124.90 |
| Emergency Protective Measures | 31 | $463,807.34 |
| Roads and Bridges | 5 | $111,515.08 |
| Management Costs | 3 | $68,111.72 |
| Water Control Facilities | 4 | $48,810.75 |
| Parks, Recreational Facilities, and Other Items | 11 | $35,886.95 |
| Buildings and Equipment | 10 | $30,708.65 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2004 | 92 |
| 2005 | 3 |
| 2008 | 1 |
| 2013 | 1 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Horry County, South Carolina | 42 | $892,721.24 |
| Georgetown County, South Carolina | 28 | $351,904.47 |
Projects FEMA labels statewide
- Project worksheets
- 27
- Federal share obligated
- $1,072,501.46
- Median days to first recorded obligation
- 52
Timing uses 27 dated worksheets and starts on the original declaration date. Earliest first obligation September 28, 2004. Most recent obligation in the project snapshot June 21, 2013.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 2 | $608,597.92 |
| Emergency Protective Measures | 9 | $216,336.63 |
| Debris Removal | 4 | $108,031.94 |
| Management Costs | 3 | $68,111.72 |
| Water Control Facilities | 4 | $48,810.75 |
| Buildings and Equipment | 3 | $19,470.00 |
| Parks, Recreational Facilities, and Other Items | 2 | $3,142.50 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2004 | 24 |
| 2005 | 2 |
| 2013 | 1 |
Project worksheet revisions
9 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 76 | July 26, 2007 | -$32,594.25 | $167,997.75 |
| Worksheet 78 | January 14, 2005 | $21,888.75 | $64,875.00 |
| Worksheet 32 | January 9, 2007 | -$14,895.00 | $0.00 |
| Worksheet 100 | January 15, 2008 | -$11,094.20 | $0.00 |
| Worksheet 77 | July 26, 2007 | -$8,622.00 | $60,762.75 |
| Worksheet 39 | September 18, 2006 | -$7,650.00 | $104,623.83 |
| Worksheet 66 | February 22, 2007 | -$5,775.00 | $38,904.00 |
| Worksheet 96 | June 5, 2012 | $2,961.80 | $101,927.26 |
| Worksheet 12 | February 25, 2013 | -$2,646.27 | $7,742.59 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.