DR-1563 · New Jersey

SEVERE STORMS AND FLOODING

Severe Storm · Declared October 1, 2004

Recorded incident start September 18, 2004. Recorded incident end October 1, 2004. Declaration request September 21, 2004. Recorded closeout April 24, 2012.

Open the official FEMA disaster page · Declaration data

County designations and filing dates

County programs listed by FEMA
CountyPrograms listedIndividual Assistance filing date
Hunterdon County, New JerseyIHP · Individual Assistance · Public Assistance · Hazard MitigationNovember 30, 2004
Mercer County, New JerseyIHP · Individual Assistance · Public Assistance · Hazard MitigationNovember 30, 2004
Sussex County, New JerseyIHP · Individual Assistance · Public Assistance · Hazard MitigationNovember 30, 2004
Warren County, New JerseyIHP · Individual Assistance · Public Assistance · Hazard MitigationNovember 30, 2004

Public Assistance for this declaration

Project worksheets
286
Federal share obligated
$4,098,435.37
Median days to first recorded obligation
133

Timing uses 286 dated worksheets and starts on the original declaration date. Earliest first obligation December 1, 2004. Most recent obligation in the project snapshot January 11, 2012.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Roads and Bridges111$2,266,262.21
Emergency Protective Measures81$759,271.80
Buildings and Equipment21$444,729.84
Debris Removal29$206,706.57
Management Costs21$191,775.27
Parks, Recreational Facilities, and Other Items10$78,931.21
Water Control Facilities4$76,532.11
Utilities9$74,226.36
First obligations by year
Year of first recorded obligation
YearWorksheets
200466
2005195
200610
20075
20084
20094
20101
20121

Projects by applicant county

Applicant location recorded by FEMA
Applicant countyWorksheetsFederal share obligated
Warren County, New Jersey141$2,286,892.23
Mercer County, New Jersey22$268,975.00
Hunterdon County, New Jersey40$167,075.89
Sussex County, New Jersey31$137,144.47

Projects FEMA labels statewide

Project worksheets
51
Federal share obligated
$1,225,104.35
Median days to first recorded obligation
154

Timing uses 51 dated worksheets and starts on the original declaration date. Earliest first obligation December 1, 2004. Most recent obligation in the project snapshot January 11, 2012.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Buildings and Equipment6$371,975.17
Emergency Protective Measures11$344,553.08
Roads and Bridges6$258,125.46
Management Costs21$191,775.27
Utilities3$30,525.00
Debris Removal2$20,330.96
Parks, Recreational Facilities, and Other Items2$7,819.41
First obligations by year
Year of first recorded obligation
YearWorksheets
20043
200527
20066
20075
20084
20094
20101
20121

Project worksheet revisions

35 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 282November 21, 2007$153,780.71$336,560.59
Worksheet 17January 28, 2009-$149,472.95$13,225.63
Worksheet 177January 28, 2008-$98,582.66$425,907.97
Worksheet 13October 24, 2005$67,067.25$111,459.14
Worksheet 194January 28, 2008-$46,555.19$5,320.89
Worksheet 280November 21, 2007$42,218.14$76,717.84
Worksheet 243July 25, 2011$40,473.38$40,473.38
Worksheet 179March 28, 2006$32,009.21$32,009.21
Worksheet 244July 25, 2011$30,346.58$30,346.58
Worksheet 157November 21, 2007-$23,063.09$72,486.91
Worksheet 1March 28, 2006$21,705.00$42,292.50
Worksheet 279November 21, 2007$18,300.00$29,459.68

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.