DR-1678 · Management Costs

Project worksheet 1214

SEVERE WINTER STORMS · Oklahoma

Applicant location · Statewide as listed by FEMA. Applicant ID 000-00641-00 · FEMA Grants Manager project 510122.

Federal share in project snapshot
$395,189.22
Net of dated activity records
$395,189.22
Dated versions
26

Declaration February 1, 2007. First obligation in the project snapshot December 20, 2007. Last obligation in that snapshot August 27, 2015.

The recorded activity sums to the project snapshot amount.

Signed obligation history

Federal share changes in FEMA award activity
Worksheet versionObligation dateSigned federal share changeRunning net in the activity file
0December 20, 2007$64,366.76$64,366.76
1March 20, 2008$35,566.10$99,932.86
2April 2, 2008$99,999.75$199,932.61
3May 1, 2008$29,748.83$229,681.44
4November 25, 2008$38,230.80$267,912.24
5June 9, 2009$32,656.81$300,569.05
6June 17, 2009-$32,656.81$267,912.24
7June 19, 2009$43,601.64$311,513.88
8January 6, 2010$39,759.68$351,273.56
9September 10, 2010$19,783.24$371,056.80
10November 17, 2010$4,975.94$376,032.74
11November 24, 2010$7,511.91$383,544.65
12January 6, 2011$931.37$384,476.02
13April 8, 2011$2,749.83$387,225.85
14December 13, 2011$2,131.25$389,357.10
15December 16, 2011$2,190.48$391,547.58
16April 9, 2012$2,327.85$393,875.43
17May 23, 2012$588.41$394,463.84
18October 4, 2012$292.71$394,756.55
19March 18, 2013$193.66$394,950.21
20April 22, 2013-$56,595.90$338,354.31
21September 23, 2013$56,595.90$394,950.21
22April 4, 2014$72.51$395,022.72
23October 7, 2014$166.50$395,189.22
24August 10, 2015$767.06$395,956.28
25August 27, 2015-$767.06$395,189.22

FEMA activity query · FEMA project query · Official disaster page

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.