DR-1801 · North Carolina
TROPICAL STORM HANNA
Severe Storm · Declared October 8, 2008
Recorded incident start September 4, 2008. Recorded incident end September 15, 2008. Declaration request September 30, 2008. Recorded closeout January 12, 2018.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Beaufort County, North Carolina | Public Assistance · Hazard Mitigation | Unavailable |
| Brunswick County, North Carolina | Public Assistance · Hazard Mitigation | Unavailable |
| New Hanover County, North Carolina | Public Assistance · Hazard Mitigation | Unavailable |
| Person County, North Carolina | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 111
- Federal share obligated
- $4,657,982.00
- Median days to first recorded obligation
- 76
Timing uses 111 dated worksheets and starts on the original declaration date. Earliest first obligation November 14, 2008. Most recent obligation in the project snapshot December 13, 2017.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Parks, Recreational Facilities, and Other Items | 8 | $1,819,370.30 |
| Roads and Bridges | 2 | $955,495.81 |
| Emergency Protective Measures | 56 | $907,794.55 |
| Debris Removal | 29 | $532,988.72 |
| Utilities | 8 | $286,174.51 |
| Management Costs | 3 | $145,604.82 |
| Buildings and Equipment | 4 | $8,678.29 |
| Water Control Facilities | 1 | $1,875.00 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2008 | 64 |
| 2009 | 45 |
| 2011 | 1 |
| 2017 | 1 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Brunswick County, North Carolina | 55 | $2,200,070.96 |
| New Hanover County, North Carolina | 20 | $688,280.26 |
| Beaufort County, North Carolina | 16 | $127,482.56 |
Projects FEMA labels statewide
- Project worksheets
- 17
- Federal share obligated
- $1,557,791.93
- Median days to first recorded obligation
- 331
Timing uses 17 dated worksheets and starts on the original declaration date. Earliest first obligation November 20, 2008. Most recent obligation in the project snapshot December 13, 2017.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 2 | $955,495.81 |
| Utilities | 2 | $214,136.83 |
| Emergency Protective Measures | 8 | $146,236.26 |
| Management Costs | 3 | $145,604.82 |
| Debris Removal | 2 | $96,318.21 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2008 | 4 |
| 2009 | 11 |
| 2011 | 1 |
| 2017 | 1 |
Project worksheet revisions
31 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 6 | September 4, 2009 | -$209,091.08 | $0.00 |
| Worksheet 104 | March 10, 2011 | -$113,309.66 | $775,975.09 |
| Worksheet 115 | June 15, 2011 | $60,276.74 | $92,456.63 |
| Worksheet 82 | February 11, 2010 | -$33,387.14 | $0.00 |
| Worksheet 14 | September 4, 2009 | -$24,087.86 | $0.00 |
| Worksheet 31 | September 4, 2009 | -$21,824.28 | $0.00 |
| Worksheet 44 | January 9, 2009 | -$20,765.83 | $0.00 |
| Worksheet 30 | September 4, 2009 | -$18,515.83 | $0.00 |
| Worksheet 4 | April 27, 2011 | $17,583.11 | $84,356.29 |
| Worksheet 102 | October 20, 2010 | -$17,540.40 | $1,651,412.88 |
| Worksheet 3 | September 4, 2009 | -$10,421.09 | $0.00 |
| Worksheet 59 | May 3, 2012 | $10,162.97 | $101,034.35 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.