DR-1934 · Missouri

Holt County, Missouri

SEVERE STORMS, FLOODING, AND TORNADOES · Declared August 17, 2010

Programs listed for this county · Public Assistance · Hazard Mitigation

Official FEMA disaster page · Other declarations for this county

Public Assistance for applicants listed in this county

Project worksheets
53
Federal share obligated
$858,804.29
Median days to first recorded obligation
90

Timing uses 53 dated worksheets and starts on the original declaration date. Earliest first obligation October 6, 2010. Most recent obligation in the project snapshot February 28, 2013.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Roads and Bridges16$499,701.83
Emergency Protective Measures17$201,929.80
Debris Removal12$125,593.99
Buildings and Equipment6$28,709.53
Utilities2$2,869.14
First obligations by year
Year of first recorded obligation
YearWorksheets
201044
20119

Revisions for worksheets with applicants in this county

5 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 578July 24, 2012-$107,887.00$0.00
Worksheet 576February 28, 2013-$69,997.50$58,650.00
Worksheet 1047February 9, 2011-$22,171.62$0.00
Worksheet 1048January 8, 2013-$15,318.60$45,955.80
Worksheet 229December 16, 2011$84.00$63,922.50

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.