DR-1951 · Vermont
SEVERE STORM
Severe Storm · Declared December 22, 2010
Recorded incident start December 1, 2010. Recorded incident end December 5, 2010. Declaration request December 10, 2010. Recorded closeout June 12, 2017.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Chittenden County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Franklin County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Lamoille County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 51
- Federal share obligated
- $1,555,019.55
- Median days to first recorded obligation
- 64
Timing uses 51 dated worksheets and starts on the original declaration date. Earliest first obligation February 3, 2011. Most recent obligation in the project snapshot December 13, 2016.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Emergency Protective Measures | 17 | $740,504.14 |
| Utilities | 7 | $390,139.42 |
| Debris Removal | 17 | $387,491.06 |
| Management Costs | 1 | $28,204.83 |
| Buildings and Equipment | 6 | $5,909.72 |
| Parks, Recreational Facilities, and Other Items | 2 | $1,973.39 |
| Roads and Bridges | 1 | $796.99 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2011 | 51 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Lamoille County, Vermont | 17 | $1,264,581.33 |
| Franklin County, Vermont | 11 | $137,511.92 |
| Chittenden County, Vermont | 22 | $124,721.47 |
Project worksheet revisions
4 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 24 | December 13, 2016 | -$22,791.17 | $28,204.83 |
| Worksheet 44 | May 27, 2011 | $4,139.92 | $143,076.15 |
| Worksheet 28 | April 6, 2011 | -$3,543.22 | $0.00 |
| Worksheet 38 | March 28, 2011 | -$2,414.25 | $0.00 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.