America.co

DR-1956 · Oregon

SEVERE WINTER STORM, FLOODING, MUDSLIDES, LANDSLIDES, AND DEBRIS FLOWS

Severe Storm · Declared February 17, 2011

Recorded incident start January 13, 2011. Recorded incident end January 21, 2011. Declaration request February 9, 2011. Recorded closeout September 29, 2017.

Open the official FEMA disaster page · Declaration data

County designations and filing dates

County programs listed by FEMA
CountyPrograms listedIndividual Assistance filing date
Clackamas County, OregonPublic Assistance · Hazard MitigationUnavailable
Clatsop County, OregonPublic Assistance · Hazard MitigationUnavailable
Crook County, OregonPublic Assistance · Hazard MitigationUnavailable
Douglas County, OregonPublic Assistance · Hazard MitigationUnavailable
Lincoln County, OregonPublic Assistance · Hazard MitigationUnavailable
Tillamook County, OregonPublic Assistance · Hazard MitigationUnavailable

Public Assistance for this declaration

Project worksheets
103
Federal share obligated
$3,990,138.12
Median days to first recorded obligation
63

Timing uses 103 dated worksheets and starts on the original declaration date. Earliest first obligation April 2, 2011. Most recent obligation in the project snapshot August 1, 2016.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Roads and Bridges52$2,639,961.19
Utilities12$905,802.10
Emergency Protective Measures22$179,141.52
Management Costs1$144,075.65
Parks, Recreational Facilities, and Other Items6$84,791.78
Debris Removal8$32,553.58
Buildings and Equipment2$3,812.30
First obligations by year
Year of first recorded obligation
YearWorksheets
2011103

Projects by applicant county

Applicant location recorded by FEMA
Applicant countyWorksheetsFederal share obligated
Clackamas County, Oregon16$1,752,801.54
Lincoln County, Oregon21$770,523.82
Tillamook County, Oregon37$765,063.70
Clatsop County, Oregon4$230,925.69
Crook County, Oregon10$151,740.68
Douglas County, Oregon7$107,607.76

Projects FEMA labels statewide

Project worksheets
2
Federal share obligated
$145,950.65
Median days to first recorded obligation
81

Timing uses 2 dated worksheets and starts on the original declaration date. Earliest first obligation April 28, 2011. Most recent obligation in the project snapshot August 1, 2016.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Management Costs1$144,075.65
Buildings and Equipment1$1,875.00
First obligations by year
Year of first recorded obligation
YearWorksheets
20112

Project worksheet revisions

15 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 80December 31, 2015$286,390.77$386,365.77
Worksheet 65April 30, 2015-$158,266.11$491,838.63
Worksheet 55February 27, 2012-$155,756.24$125,037.26
Worksheet 53August 20, 2012-$67,868.68$86,712.64
Worksheet 61January 13, 2012-$33,870.18$54,348.57
Worksheet 103December 22, 2015$26,082.04$960,689.63
Worksheet 83May 19, 2014-$18,051.00$0.00
Worksheet 26March 14, 2014$14,045.84$40,295.84
Worksheet 84May 19, 2014-$9,766.50$0.00
Worksheet 102August 24, 2012-$7,539.90$95,927.10
Worksheet 101December 22, 2015$7,506.14$76,745.29
Worksheet 12October 18, 2012-$7,088.67$0.00

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.

FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity