DR-1981 · North Dakota

LaMoure County, North Dakota

FLOODING · Declared May 10, 2011

Programs listed for this county · Public Assistance · Hazard Mitigation

FEMA Individual Assistance filing date · November 21, 2011

Official FEMA disaster page · Other declarations for this county

Public Assistance for applicants listed in this county

Project worksheets
60
Federal share obligated
$998,527.34
Median days to first recorded obligation
266.5

Timing uses 60 dated worksheets and starts on the original declaration date. Earliest first obligation August 15, 2011. Most recent obligation in the project snapshot January 11, 2016.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Roads and Bridges50$916,197.73
Emergency Protective Measures10$82,329.61
First obligations by year
Year of first recorded obligation
YearWorksheets
201116
201244

Revisions for worksheets with applicants in this county

9 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 1012June 6, 2012-$111,916.40$4,898.58
Worksheet 1035April 10, 2013-$89,900.17$3,658.92
Worksheet 1064February 20, 2015-$29,402.24$118,394.45
Worksheet 3271January 11, 2016-$5,863.95$17,777.58
Worksheet 1738August 21, 2015$5,628.61$145,810.24
Worksheet 4429January 11, 2016-$4,999.05$14,639.00
Worksheet 4260January 11, 2016-$3,245.40$10,327.43
Worksheet 4539January 11, 2016-$1,237.50$18,942.63
Worksheet 4068January 11, 2016-$1,200.15$20,758.52

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.