DR-1995 · Vermont
SEVERE STORMS AND FLOODING
Severe Storm · Declared June 15, 2011
Recorded incident start April 23, 2011. Recorded incident end May 9, 2011. Declaration request May 27, 2011. Recorded closeout June 11, 2026.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Addison County, Vermont | IHP · Public Assistance · Hazard Mitigation | August 15, 2011 |
| Chittenden County, Vermont | IHP · Public Assistance · Hazard Mitigation | August 15, 2011 |
| Essex County, Vermont | IHP · Public Assistance · Hazard Mitigation | August 15, 2011 |
| Franklin County, Vermont | IHP · Public Assistance · Hazard Mitigation | August 15, 2011 |
| Grand Isle County, Vermont | IHP · Public Assistance · Hazard Mitigation | August 15, 2011 |
| Lamoille County, Vermont | IHP · Public Assistance · Hazard Mitigation | August 15, 2011 |
| Orleans County, Vermont | IHP · Public Assistance · Hazard Mitigation | August 15, 2011 |
| Washington County, Vermont | Public Assistance · Hazard Mitigation | August 15, 2011 |
Public Assistance for this declaration
- Project worksheets
- 550
- Federal share obligated
- $14,747,309.61
- Median days to first recorded obligation
- 114
Timing uses 550 dated worksheets and starts on the original declaration date. Earliest first obligation July 22, 2011. Most recent obligation in the project snapshot May 4, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Parks, Recreational Facilities, and Other Items | 100 | $9,078,126.12 |
| Roads and Bridges | 368 | $4,270,996.64 |
| Utilities | 16 | $520,524.17 |
| Emergency Protective Measures | 40 | $499,638.27 |
| Management Costs | 1 | $202,297.02 |
| Debris Removal | 14 | $88,019.56 |
| Buildings and Equipment | 11 | $87,707.83 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2011 | 482 |
| 2012 | 63 |
| 2013 | 5 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Washington County, Vermont | 45 | $7,837,564.51 |
| Chittenden County, Vermont | 103 | $2,460,958.28 |
| Orleans County, Vermont | 94 | $1,111,247.93 |
| Lamoille County, Vermont | 105 | $992,903.78 |
| Grand Isle County, Vermont | 35 | $642,564.40 |
| Essex County, Vermont | 25 | $391,201.97 |
| Franklin County, Vermont | 27 | $290,862.31 |
| Addison County, Vermont | 42 | $288,312.48 |
Projects FEMA labels statewide
- Project worksheets
- 74
- Federal share obligated
- $731,693.95
- Median days to first recorded obligation
- 135
Timing uses 74 dated worksheets and starts on the original declaration date. Earliest first obligation August 15, 2011. Most recent obligation in the project snapshot November 19, 2014.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Parks, Recreational Facilities, and Other Items | 42 | $500,238.43 |
| Roads and Bridges | 16 | $141,483.62 |
| Buildings and Equipment | 9 | $65,334.01 |
| Debris Removal | 5 | $18,758.68 |
| Emergency Protective Measures | 2 | $5,879.21 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2011 | 58 |
| 2012 | 16 |
Project worksheet revisions
36 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 548 | January 28, 2026 | $1,403,075.79 | $1,871,645.94 |
| Worksheet 538 | January 15, 2021 | $355,742.14 | $1,326,336.44 |
| Worksheet 524 | January 17, 2017 | -$327,409.58 | $0.00 |
| Worksheet 547 | November 26, 2025 | -$181,029.38 | $1,428,988.16 |
| Worksheet 437 | October 18, 2013 | $142,410.00 | $237,486.75 |
| Worksheet 436 | May 8, 2014 | -$139,971.52 | $446,337.23 |
| Worksheet 39 | May 4, 2026 | -$130,449.98 | $202,297.02 |
| Worksheet 525 | February 1, 2013 | -$95,665.59 | $0.00 |
| Worksheet 505 | November 19, 2014 | $89,291.18 | $126,262.51 |
| Worksheet 527 | December 18, 2012 | -$82,807.90 | $0.00 |
| Worksheet 400 | May 22, 2017 | -$67,730.25 | $203,190.75 |
| Worksheet 100 | March 4, 2013 | $57,892.04 | $125,448.70 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.