DR-4001 · Vermont
SEVERE STORMS AND FLOODING
Severe Storm · Declared July 8, 2011
Recorded incident start May 26, 2011. Recorded incident end May 27, 2011. Declaration request June 3, 2011. Recorded closeout March 20, 2020.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Caledonia County, Vermont | IHP · Public Assistance · Hazard Mitigation | September 6, 2011 |
| Essex County, Vermont | Public Assistance · Hazard Mitigation | September 6, 2011 |
| Orange County, Vermont | Public Assistance · Hazard Mitigation | September 6, 2011 |
| Washington County, Vermont | IHP · Public Assistance · Hazard Mitigation | September 6, 2011 |
Public Assistance for this declaration
- Project worksheets
- 558
- Federal share obligated
- $10,545,798.69
- Median days to first recorded obligation
- 167
Timing uses 558 dated worksheets and starts on the original declaration date. Earliest first obligation August 23, 2011. Most recent obligation in the project snapshot December 9, 2019.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 482 | $7,408,100.37 |
| Utilities | 7 | $1,862,538.50 |
| Parks, Recreational Facilities, and Other Items | 33 | $805,803.66 |
| Emergency Protective Measures | 21 | $252,584.03 |
| Management Costs | 1 | $107,720.79 |
| Buildings and Equipment | 6 | $52,232.55 |
| Debris Removal | 6 | $48,301.97 |
| Water Control Facilities | 2 | $8,516.82 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2011 | 324 |
| 2012 | 227 |
| 2013 | 7 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Washington County, Vermont | 273 | $5,634,948.61 |
| Caledonia County, Vermont | 160 | $2,799,333.44 |
| Essex County, Vermont | 64 | $1,396,986.13 |
| Orange County, Vermont | 28 | $167,666.71 |
Projects FEMA labels statewide
- Project worksheets
- 30
- Federal share obligated
- $487,216.87
- Median days to first recorded obligation
- 120.5
Timing uses 30 dated worksheets and starts on the original declaration date. Earliest first obligation October 5, 2011. Most recent obligation in the project snapshot February 19, 2013.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 15 | $355,384.71 |
| Parks, Recreational Facilities, and Other Items | 14 | $117,936.66 |
| Emergency Protective Measures | 1 | $13,895.50 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2011 | 28 |
| 2012 | 2 |
Project worksheet revisions
26 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 158 | May 29, 2019 | -$184,137.21 | $107,720.79 |
| Worksheet 551 | March 1, 2019 | $108,400.10 | $157,483.10 |
| Worksheet 490 | September 1, 2016 | $80,139.97 | $1,786,589.85 |
| Worksheet 7 | January 18, 2012 | -$73,145.63 | $212,647.57 |
| Worksheet 554 | November 23, 2018 | -$39,541.33 | $74,551.71 |
| Worksheet 92 | March 7, 2012 | $32,892.87 | $39,389.81 |
| Worksheet 33 | January 7, 2013 | -$28,957.28 | $78,975.22 |
| Worksheet 209 | September 9, 2013 | -$28,729.40 | $0.00 |
| Worksheet 154 | May 18, 2012 | -$26,691.10 | $57,069.83 |
| Worksheet 547 | February 7, 2013 | $24,546.44 | $86,250.01 |
| Worksheet 198 | May 30, 2013 | $19,856.51 | $75,555.26 |
| Worksheet 448 | August 9, 2013 | -$17,527.46 | $125,510.25 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.