America.co

DR-4143 · Arkansas

SEVERE STORMS AND FLOODING

Severe Storm · Declared September 4, 2013

Recorded incident start August 8, 2013. Recorded incident end August 14, 2013. Declaration request August 27, 2013. Recorded closeout May 17, 2022.

Open the official FEMA disaster page · Declaration data

County designations and filing dates

County programs listed by FEMA
CountyPrograms listedIndividual Assistance filing date
Benton County, ArkansasPublic Assistance · Hazard MitigationUnavailable
Boone County, ArkansasPublic Assistance · Hazard MitigationUnavailable
Carroll County, ArkansasPublic Assistance · Hazard MitigationUnavailable
Madison County, ArkansasPublic Assistance · Hazard MitigationUnavailable
Marion County, ArkansasPublic Assistance · Hazard MitigationUnavailable
Newton County, ArkansasPublic Assistance · Hazard MitigationUnavailable

Public Assistance for this declaration

Project worksheets
116
Federal share obligated
$7,781,424.57
Median days to first recorded obligation
155

Timing uses 116 dated worksheets and starts on the original declaration date. Earliest first obligation December 18, 2013. Most recent obligation in the project snapshot April 28, 2022.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Roads and Bridges104$7,541,700.17
Utilities5$158,917.08
Management Costs1$61,607.32
Parks, Recreational Facilities, and Other Items2$13,352.62
Debris Removal1$3,383.33
Emergency Protective Measures3$2,464.05
First obligations by year
Year of first recorded obligation
YearWorksheets
20136
2014108
20151
20161

Projects by applicant county

Applicant location recorded by FEMA
Applicant countyWorksheetsFederal share obligated
Benton County, Arkansas41$3,234,867.75
Newton County, Arkansas29$2,222,624.56
Marion County, Arkansas13$790,779.04
Madison County, Arkansas5$503,524.72
Boone County, Arkansas9$484,443.93
Carroll County, Arkansas16$404,410.98

Projects FEMA labels statewide

Project worksheets
2
Federal share obligated
$123,766.39
Median days to first recorded obligation
218

Timing uses 2 dated worksheets and starts on the original declaration date. Earliest first obligation February 6, 2014. Most recent obligation in the project snapshot April 28, 2022.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Utilities1$62,159.07
Management Costs1$61,607.32
First obligations by year
Year of first recorded obligation
YearWorksheets
20142

Project worksheet revisions

33 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 118April 28, 2022-$226,002.27$217,414.21
Worksheet 116April 28, 2022-$197,434.68$61,607.32
Worksheet 65October 1, 2015-$32,143.54$228,506.89
Worksheet 77April 20, 2016-$31,108.00$142,936.21
Worksheet 113November 17, 2021-$30,255.63$62,827.45
Worksheet 88February 11, 2015$29,021.70$184,345.49
Worksheet 78October 1, 2015-$23,000.35$165,930.46
Worksheet 17October 15, 2014-$22,411.48$49,375.84
Worksheet 91November 17, 2021-$20,563.88$80,849.82
Worksheet 19February 11, 2015$18,345.83$73,682.10
Worksheet 49May 19, 2015$17,405.54$106,370.32
Worksheet 84November 17, 2021-$12,998.51$37,959.64

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.

FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity