DR-4152 · New Mexico

McKinley County, New Mexico

SEVERE STORMS, FLOODING, AND MUDSLIDES · Declared October 29, 2013

Programs listed for this county · Public Assistance · Hazard Mitigation

Official FEMA disaster page · Other declarations for this county

Public Assistance for applicants listed in this county

Project worksheets
32
Federal share obligated
$811,628.71
Median days to first recorded obligation
135

Timing uses 32 dated worksheets and starts on the original declaration date. Earliest first obligation January 30, 2014. Most recent obligation in the project snapshot November 11, 2021.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Buildings and Equipment1$619,405.22
Roads and Bridges29$186,958.74
Emergency Protective Measures1$4,248.41
Debris Removal1$1,016.34
First obligations by year
Year of first recorded obligation
YearWorksheets
201431
20191

Revisions for worksheets with applicants in this county

16 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 301January 11, 2019-$282,896.66$0.00
Worksheet 313January 11, 2019-$275,722.20$0.00
Worksheet 306January 11, 2019-$118,948.74$0.00
Worksheet 303January 11, 2019-$85,469.60$0.00
Worksheet 307January 11, 2019-$53,392.05$0.00
Worksheet 315January 11, 2019-$37,811.00$0.00
Worksheet 100January 11, 2019-$32,471.15$0.00
Worksheet 41January 11, 2019-$24,207.41$0.00
Worksheet 101February 12, 2018-$21,445.14$0.00
Worksheet 310June 25, 2021-$20,108.41$16,300.51
Worksheet 50November 29, 2016-$17,621.96$0.00
Worksheet 18August 2, 2016$11,535.00$17,022.27

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.