DR-4159 · Texas
SEVERE STORMS AND FLOODING
Severe Storm · Declared December 20, 2013
Recorded incident start October 30, 2013. Recorded incident end October 31, 2013. Declaration request December 12, 2013.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Caldwell County, Texas | Public Assistance · Hazard Mitigation | Unavailable |
| Freestone County, Texas | Public Assistance · Hazard Mitigation | Unavailable |
| Hays County, Texas | Public Assistance · Hazard Mitigation | Unavailable |
| Travis County, Texas | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 134
- Federal share obligated
- $7,753,470.35
- Median days to first recorded obligation
- 144
Timing uses 134 dated worksheets and starts on the original declaration date. Earliest first obligation April 1, 2014. Most recent obligation in the project snapshot January 9, 2024.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 36 | $2,199,489.29 |
| Debris Removal | 17 | $1,529,826.64 |
| Parks, Recreational Facilities, and Other Items | 25 | $1,083,985.69 |
| Utilities | 12 | $1,060,647.89 |
| Emergency Protective Measures | 20 | $698,835.44 |
| Water Control Facilities | 9 | $619,663.73 |
| Management Costs | 1 | $339,720.00 |
| Buildings and Equipment | 14 | $221,301.67 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2014 | 126 |
| 2015 | 5 |
| 2018 | 1 |
| 2020 | 2 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Travis County, Texas | 53 | $5,309,885.05 |
| Hays County, Texas | 37 | $999,453.32 |
| Freestone County, Texas | 14 | $426,654.03 |
| Caldwell County, Texas | 16 | $300,849.00 |
Projects FEMA labels statewide
- Project worksheets
- 14
- Federal share obligated
- $716,628.95
- Median days to first recorded obligation
- 174
Timing uses 14 dated worksheets and starts on the original declaration date. Earliest first obligation April 1, 2014. Most recent obligation in the project snapshot August 14, 2020.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Management Costs | 1 | $339,720.00 |
| Emergency Protective Measures | 5 | $123,925.26 |
| Water Control Facilities | 1 | $101,803.64 |
| Debris Removal | 2 | $95,314.79 |
| Parks, Recreational Facilities, and Other Items | 2 | $43,978.66 |
| Utilities | 1 | $11,886.60 |
| Buildings and Equipment | 2 | $0.00 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2014 | 10 |
| 2015 | 2 |
| 2020 | 2 |
Project worksheet revisions
50 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 96 | February 10, 2017 | -$647,152.50 | $0.00 |
| Worksheet 138 | February 10, 2017 | -$326,028.68 | $0.00 |
| Worksheet 58 | April 10, 2018 | -$177,836.75 | $399,355.75 |
| Worksheet 132 | September 17, 2018 | -$108,056.61 | $399,914.89 |
| Worksheet 91 | June 11, 2016 | -$92,331.75 | $0.00 |
| Worksheet 57 | March 7, 2017 | -$59,844.89 | $14,654.89 |
| Worksheet 45 | June 17, 2019 | -$55,048.50 | $4,147.50 |
| Worksheet 108 | December 15, 2023 | $50,898.92 | $249,855.85 |
| Worksheet 109 | June 11, 2016 | -$48,866.02 | $0.00 |
| Worksheet 11 | April 6, 2016 | -$45,104.40 | $0.00 |
| Worksheet 117 | November 22, 2016 | $41,563.46 | $102,333.99 |
| Worksheet 105 | July 27, 2020 | -$36,316.26 | $389,021.39 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.