| Worksheet | Applicant location | Work category | Last activity date | Last signed change | Federal share in project snapshot |
|---|---|---|---|---|---|
| 1 | Statewide | Emergency Protective Measures | January 9, 2024 | -$0.01 | $1,135,997.20 |
| 2 | Statewide | Management Costs | March 14, 2018 | $8,032,047.00 | $9,809,498.00 |
| 3 | Statewide | Emergency Protective Measures | December 21, 2018 | $1,057,457.72 | $3,981,763.93 |
| 4 | Edgecombe County, North Carolina | Emergency Protective Measures | August 21, 2024 | -$158,675.99 | $0.00 |
| 15 | Statewide | Emergency Protective Measures | May 8, 2017 | $6,177.80 | $21,242.77 |
| 18 | Statewide | Emergency Protective Measures | April 27, 2017 | $12,265.14 | $84,360.39 |
| 21 | Statewide | Emergency Protective Measures | February 25, 2026 | $257,035.95 | $408,953.95 |
| 24 | Statewide | Emergency Protective Measures | January 8, 2024 | -$0.01 | $139,271.22 |
| 25 | Statewide | Emergency Protective Measures | April 11, 2023 | -$193,459.58 | $348,067.41 |
| 26 | Statewide | Emergency Protective Measures | February 13, 2023 | $84,415.99 | $281,164.83 |
| 34 | Wayne County, North Carolina | Utilities | January 9, 2024 | -$0.01 | $20,853.40 |
| 39 | Edgecombe County, North Carolina | Parks, Recreational Facilities, and Other Items | October 31, 2023 | $4,914.01 | $125,514.47 |
| 41 | Cumberland County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $5,923.00 |
| 61 | Robeson County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $166,897.52 |
| 64 | Statewide | Emergency Protective Measures | January 9, 2024 | -$0.01 | $2,355.88 |
| 65 | Edgecombe County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $4,228.66 |
| 84 | Edgecombe County, North Carolina | Buildings and Equipment | May 4, 2022 | $465,097.19 | $507,246.27 |
| 86 | Onslow County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $4,291.00 |
| 88 | Edgecombe County, North Carolina | Buildings and Equipment | March 19, 2025 | $604,530.53 | $868,628.75 |
| 89 | Johnston County, North Carolina | Debris Removal | January 8, 2024 | -$0.01 | $9,732.64 |
| 96 | Onslow County, North Carolina | Parks, Recreational Facilities, and Other Items | January 9, 2024 | -$0.01 | $1,660.18 |
| 117 | Edgecombe County, North Carolina | Buildings and Equipment | December 18, 2020 | -$21,467.57 | $141,412.30 |
| 119 | Sampson County, North Carolina | Roads and Bridges | October 3, 2017 | $967.50 | $17,123.22 |
| 128 | Robeson County, North Carolina | Buildings and Equipment | January 8, 2024 | -$0.01 | $13,043.32 |
| 137 | Beaufort County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $17,237.86 |
| 150 | Anson County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $4,639.60 |
| 157 | Edgecombe County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $54,146.38 |
| 158 | Statewide | Buildings and Equipment | January 9, 2024 | -$0.01 | $74,415.52 |
| 160 | Brunswick County, North Carolina | Parks, Recreational Facilities, and Other Items | January 9, 2024 | -$0.01 | $3,054.82 |
| 161 | Brunswick County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $5,828.26 |
| 163 | Brunswick County, North Carolina | Debris Removal | June 24, 2017 | -$51,113.69 | $0.00 |
| 176 | Dare County, North Carolina | Buildings and Equipment | April 22, 2017 | $487.50 | $3,787.50 |
| 185 | Pitt County, North Carolina | Debris Removal | July 18, 2017 | $1,877.65 | $10,498.73 |
| 193 | Edgecombe County, North Carolina | Debris Removal | May 8, 2020 | $2,689.03 | $169,711.21 |
| 208 | Harnett County, North Carolina | Debris Removal | March 29, 2017 | -$2,232.98 | $35,727.71 |
| 213 | Nash County, North Carolina | Buildings and Equipment | August 23, 2017 | -$8,538.00 | $9,961.12 |
| 215 | Pender County, North Carolina | Parks, Recreational Facilities, and Other Items | January 8, 2024 | -$0.01 | $2,348.62 |
| 216 | Hoke County, North Carolina | Debris Removal | November 27, 2017 | -$44.00 | $100,569.84 |
| 220 | Onslow County, North Carolina | Debris Removal | March 29, 2017 | $16,512.54 | $140,356.60 |
| 228 | Duplin County, North Carolina | Utilities | April 16, 2018 | $1,553.84 | $114,842.23 |
| 231 | Robeson County, North Carolina | Debris Removal | January 8, 2024 | -$0.01 | $34,146.15 |
| 232 | Anson County, North Carolina | Utilities | January 8, 2024 | -$0.01 | $336,687.00 |
| 252 | Brunswick County, North Carolina | Debris Removal | March 29, 2017 | $2,267.64 | $16,290.14 |
| 258 | Edgecombe County, North Carolina | Parks, Recreational Facilities, and Other Items | January 9, 2024 | -$0.01 | $199.42 |
| 259 | Statewide | Debris Removal | October 10, 2025 | $2,184.34 | $149,037.42 |
| 260 | Robeson County, North Carolina | Utilities | June 20, 2018 | $14,338.30 | $154,628.58 |
| 261 | Edgecombe County, North Carolina | Utilities | May 30, 2026 | -$62,327.37 | $127,676.41 |
| 269 | Sampson County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $3,212.56 |
| 270 | Robeson County, North Carolina | Utilities | May 1, 2023 | $103,711.05 | $1,523,914.52 |
| 271 | Edgecombe County, North Carolina | Utilities | June 8, 2022 | -$76,658.02 | $331,184.06 |
| 298 | Robeson County, North Carolina | Utilities | March 4, 2021 | $32,772.87 | $238,236.12 |
| 300 | Onslow County, North Carolina | Utilities | April 30, 2020 | -$1,983.81 | $930,817.47 |
| 303 | Wilson County, North Carolina | Buildings and Equipment | January 9, 2024 | -$0.01 | $2,967.10 |
| 304 | Robeson County, North Carolina | Emergency Protective Measures | August 23, 2021 | $139,792.22 | $411,032.89 |
| 323 | Dare County, North Carolina | Parks, Recreational Facilities, and Other Items | October 5, 2018 | -$11,590.44 | $202,834.56 |
| 332 | Brunswick County, North Carolina | Emergency Protective Measures | April 5, 2021 | -$362,848.47 | $3,640,686.03 |
| 338 | Edgecombe County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $10,110.34 |
| 339 | Robeson County, North Carolina | Utilities | January 8, 2024 | -$0.01 | $342,034.61 |
| 344 | Robeson County, North Carolina | Debris Removal | August 24, 2019 | -$55,571.19 | $1,003,435.20 |
| 350 | Craven County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $139,853.78 |
| 352 | Wilson County, North Carolina | Parks, Recreational Facilities, and Other Items | January 9, 2024 | -$0.01 | $13,345.06 |
| 353 | Martin County, North Carolina | Debris Removal | April 18, 2017 | $1,658.64 | $23,107.87 |
| 373 | Brunswick County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $272,008.58 |
| 383 | Wake County, North Carolina | Buildings and Equipment | April 5, 2021 | -$224.89 | $460,049.54 |
| 400 | Scotland County, North Carolina | Buildings and Equipment | July 7, 2021 | -$3,850.46 | $103,229.21 |
| 403 | Statewide | Utilities | January 8, 2024 | -$0.01 | $127,999.34 |
| 405 | Johnston County, North Carolina | Buildings and Equipment | June 20, 2018 | $4,665.52 | $5,485.97 |
| 408 | Lenoir County, North Carolina | Utilities | November 13, 2020 | $2,077.93 | $308,765.02 |
| 429 | Cumberland County, North Carolina | Buildings and Equipment | December 19, 2023 | -$24,741.03 | $0.00 |
| 431 | Onslow County, North Carolina | Parks, Recreational Facilities, and Other Items | April 5, 2021 | -$542,963.39 | $4,728,034.36 |
| 435 | Duplin County, North Carolina | Debris Removal | March 29, 2017 | $5,942.18 | $50,508.50 |
| 443 | Brunswick County, North Carolina | Debris Removal | April 16, 2018 | $74,254.58 | $347,359.55 |
| 446 | Bladen County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $12,988.36 |
| 448 | Moore County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $13,088.38 |
| 449 | Greene County, North Carolina | Parks, Recreational Facilities, and Other Items | January 8, 2024 | -$0.01 | $7,405.66 |
| 458 | Duplin County, North Carolina | Buildings and Equipment | May 30, 2018 | -$740.41 | $7,413.67 |
| 459 | Brunswick County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $4,589.62 |
| 463 | Cumberland County, North Carolina | Utilities | January 8, 2024 | -$0.01 | $7,454.08 |
| 465 | Scotland County, North Carolina | Roads and Bridges | July 7, 2021 | -$32,091.60 | $101,496.01 |
| 478 | Northampton County, North Carolina | Emergency Protective Measures | January 8, 2024 | -$0.01 | $4,176.40 |
| 497 | Washington County, North Carolina | Parks, Recreational Facilities, and Other Items | January 9, 2024 | -$0.01 | $399.94 |
| 499 | Johnston County, North Carolina | Utilities | April 19, 2021 | $15,060.00 | $122,794.52 |
| 501 | Chatham County, North Carolina | Parks, Recreational Facilities, and Other Items | January 9, 2024 | -$0.01 | $19,774.42 |
| 510 | Columbus County, North Carolina | Buildings and Equipment | June 26, 2018 | -$2,203.50 | $19,831.50 |
| 512 | Columbus County, North Carolina | Buildings and Equipment | June 26, 2018 | -$2,050.13 | $18,451.12 |
| 526 | Edgecombe County, North Carolina | Parks, Recreational Facilities, and Other Items | January 9, 2024 | -$0.01 | $2,232.52 |
| 528 | Edgecombe County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $33,766.84 |
| 533 | New Hanover County, North Carolina | Debris Removal | April 22, 2017 | -$16,510.61 | $660,424.14 |
| 537 | Statewide | Emergency Protective Measures | September 19, 2018 | -$30,209.25 | $2,005,436.63 |
| 538 | Columbus County, North Carolina | Buildings and Equipment | May 30, 2018 | -$3,718.50 | $79,200.00 |
| 558 | Chatham County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $53,877.70 |
| 561 | Brunswick County, North Carolina | Debris Removal | May 24, 2017 | $1,769.33 | $24,022.25 |
| 563 | Robeson County, North Carolina | Debris Removal | January 9, 2024 | -$0.01 | $251,859.61 |
| 565 | Cumberland County, North Carolina | Buildings and Equipment | December 19, 2023 | -$4,304.55 | $0.00 |
| 578 | Harnett County, North Carolina | Emergency Protective Measures | July 12, 2017 | $610.33 | $75,813.35 |
| 586 | Bladen County, North Carolina | Water Control Facilities | October 11, 2018 | $16,808.74 | $122,132.03 |
| 596 | Edgecombe County, North Carolina | Roads and Bridges | January 9, 2024 | -$0.01 | $321,008.36 |
| 599 | Duplin County, North Carolina | Utilities | July 14, 2020 | -$254,169.55 | $437,445.80 |
| 602 | Richmond County, North Carolina | Debris Removal | May 11, 2017 | $661.17 | $5,619.93 |
| 604 | Edgecombe County, North Carolina | Emergency Protective Measures | January 9, 2024 | -$0.01 | $2,645.62 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity