DR-4299 · Oklahoma
SEVERE WINTER STORM
Severe Storm · Declared February 10, 2017
Recorded incident start January 13, 2017. Recorded incident end January 16, 2017. Declaration request February 1, 2017. Recorded closeout September 5, 2026.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Beaver County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Beckham County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Blaine County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Dewey County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Ellis County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Harper County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Major County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Roger Mills County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Texas County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Woods County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Woodward County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 101
- Federal share obligated
- $141,444,101.76
- Median days to first recorded obligation
- 353
Timing uses 101 dated worksheets and starts on the original declaration date. Earliest first obligation April 24, 2017. Most recent obligation in the project snapshot July 1, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 19 | $133,446,931.82 |
| Management Costs | 1 | $3,886,907.34 |
| Debris Removal | 43 | $3,034,772.05 |
| Emergency Protective Measures | 31 | $725,189.07 |
| Roads and Bridges | 6 | $345,222.21 |
| Parks, Recreational Facilities, and Other Items | 1 | $5,079.27 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2017 | 46 |
| 2018 | 54 |
| 2021 | 1 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Beaver County, Oklahoma | 10 | $726,496.60 |
| Woodward County, Oklahoma | 15 | $552,783.98 |
| Dewey County, Oklahoma | 9 | $336,013.28 |
| Harper County, Oklahoma | 7 | $308,899.53 |
| Ellis County, Oklahoma | 20 | $278,071.20 |
| Texas County, Oklahoma | 5 | $253,026.23 |
| Major County, Oklahoma | 3 | $126,341.54 |
| Woods County, Oklahoma | 2 | $33,587.62 |
| Blaine County, Oklahoma | 3 | $21,024.15 |
Projects FEMA labels statewide
- Project worksheets
- 25
- Federal share obligated
- $138,184,360.54
- Median days to first recorded obligation
- 277
Timing uses 25 dated worksheets and starts on the original declaration date. Earliest first obligation April 24, 2017. Most recent obligation in the project snapshot July 1, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 13 | $132,660,428.95 |
| Management Costs | 1 | $3,886,907.34 |
| Debris Removal | 4 | $1,164,307.72 |
| Emergency Protective Measures | 7 | $472,716.53 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2017 | 14 |
| 2018 | 10 |
| 2021 | 1 |
Project worksheet revisions
42 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 53 | July 1, 2026 | $7,532,838.92 | $41,651,879.97 |
| Worksheet 80 | June 12, 2018 | $564,075.09 | $15,225,514.86 |
| Worksheet 56 | March 20, 2018 | $97,291.94 | $235,707.80 |
| Worksheet 7 | August 7, 2018 | $48,669.28 | $108,577.55 |
| Worksheet 14 | August 27, 2025 | -$45,184.66 | $3,886,907.34 |
| Worksheet 91 | March 27, 2018 | $42,166.18 | $78,553.42 |
| Worksheet 11 | January 17, 2018 | $37,068.40 | $79,789.01 |
| Worksheet 68 | March 20, 2018 | $20,869.02 | $36,020.56 |
| Worksheet 100 | March 27, 2019 | $17,061.14 | $298,798.20 |
| Worksheet 19 | March 1, 2018 | $14,821.41 | $81,402.41 |
| Worksheet 81 | March 27, 2018 | $14,487.13 | $39,766.64 |
| Worksheet 93 | March 20, 2018 | $12,033.90 | $18,346.26 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.