DR-4339 · Puerto Rico
Project worksheets 1–177
HURRICANE MARIA
Showing 1–100 of 3,062 worksheets with dated revisions, in worksheet number order.
Worksheet timelines
Jump to a worksheet number range
| Worksheet | Applicant location | Work category | Last activity date | Last signed change | Federal share in project snapshot |
|---|---|---|---|---|---|
| 1 | Statewide | Emergency Protective Measures | February 27, 2026 | $8,285,861.34 | $44,769,071.26 |
| 2 | Unavailable | Emergency Protective Measures | June 6, 2024 | $462.49 | $283,110.20 |
| 4 | Unavailable | Emergency Protective Measures | September 15, 2025 | $2,020.70 | $547,823.51 |
| 5 | Unavailable | Emergency Protective Measures | February 8, 2019 | $1,432,844.20 | $2,037,844.20 |
| 8 | Unavailable | Emergency Protective Measures | March 4, 2025 | -$290,414.64 | $419,496.94 |
| 11 | Unavailable | Emergency Protective Measures | August 17, 2026 | $85,043.42 | $3,151,818.08 |
| 13 | Unavailable | Emergency Protective Measures | March 31, 2025 | -$80,822.85 | $357,416.42 |
| 15 | Unavailable | Emergency Protective Measures | May 10, 2021 | $7,897.01 | $1,720,190.43 |
| 16 | Unavailable | Emergency Protective Measures | August 12, 2026 | -$114,284.28 | $1,075,620.08 |
| 18 | Unavailable | Emergency Protective Measures | April 22, 2025 | -$8,755.05 | $603,894.51 |
| 22 | Unavailable | Emergency Protective Measures | October 19, 2026 | -$6,883.75 | $822,927.90 |
| 23 | Unavailable | Emergency Protective Measures | August 11, 2026 | -$123,751.12 | $407,420.00 |
| 24 | Unavailable | Emergency Protective Measures | October 22, 2026 | $6,468.62 | $471,471.10 |
| 25 | Unavailable | Emergency Protective Measures | August 11, 2025 | -$1,306,152.50 | $2,050,679.07 |
| 26 | Unavailable | Emergency Protective Measures | October 20, 2023 | -$31,782.01 | $519,613.23 |
| 28 | Unavailable | Emergency Protective Measures | April 23, 2024 | -$562.83 | $624,881.11 |
| 30 | Unavailable | Emergency Protective Measures | September 28, 2023 | -$445.58 | $538,935.64 |
| 35 | Unavailable | Emergency Protective Measures | August 11, 2025 | -$804,026.72 | $1,002,528.77 |
| 36 | Unavailable | Emergency Protective Measures | August 14, 2026 | -$462,575.54 | $13,687,819.51 |
| 38 | Unavailable | Emergency Protective Measures | August 11, 2025 | -$42,549.33 | $538,374.44 |
| 42 | Statewide | Emergency Protective Measures | May 25, 2018 | $63,312.90 | $123,866.40 |
| 43 | Unavailable | Emergency Protective Measures | December 19, 2023 | -$100,377.58 | $1,559,649.86 |
| 47 | Unavailable | Emergency Protective Measures | October 21, 2024 | -$302.64 | $159,344.87 |
| 49 | Unavailable | Debris Removal | October 8, 2025 | -$73,704.06 | $4,716,242.04 |
| 50 | Unavailable | Emergency Protective Measures | July 7, 2023 | -$218.72 | $1,039,055.79 |
| 51 | Unavailable | Debris Removal | November 13, 2025 | $8,106.50 | $5,136,461.51 |
| 52 | Unavailable | Debris Removal | August 13, 2024 | -$107,238.46 | $1,165,663.42 |
| 53 | Unavailable | Debris Removal | March 31, 2025 | -$61,859.13 | $140,762.46 |
| 56 | Unavailable | Emergency Protective Measures | January 13, 2026 | -$7,559.91 | $267,215.31 |
| 57 | Unavailable | Debris Removal | August 25, 2026 | -$200,000.00 | $3,998,949.43 |
| 58 | Unavailable | Emergency Protective Measures | April 10, 2025 | -$407,353.21 | $594,304.10 |
| 61 | Unavailable | Debris Removal | May 13, 2025 | -$10,549.31 | $5,010,342.50 |
| 62 | Unavailable | Debris Removal | December 10, 2024 | -$3,768,527.30 | $2,330,648.84 |
| 63 | Statewide | Emergency Protective Measures | September 9, 2021 | -$950,000.00 | $0.00 |
| 64 | Unavailable | Debris Removal | October 9, 2025 | -$782,953.90 | $3,286,549.80 |
| 66 | Statewide | Debris Removal | May 22, 2018 | $20,300,000.00 | $21,250,000.00 |
| 67 | Unavailable | Debris Removal | August 6, 2026 | -$39,957.65 | $3,919,831.78 |
| 69 | Unavailable | Emergency Protective Measures | April 4, 2025 | -$81,206.51 | $857,403.29 |
| 71 | Unavailable | Debris Removal | May 13, 2025 | -$58,184.17 | $4,303,643.97 |
| 72 | Unavailable | Debris Removal | June 4, 2025 | -$58,371.09 | $2,641,298.73 |
| 77 | Unavailable | Debris Removal | July 13, 2026 | -$277,258.04 | $2,117,001.84 |
| 79 | Statewide | Emergency Protective Measures | April 27, 2018 | $10,768.97 | $28,499.50 |
| 80 | Statewide | Emergency Protective Measures | November 20, 2018 | $12,812.28 | $25,812.28 |
| 82 | Statewide | Emergency Protective Measures | August 12, 2025 | -$45,264.42 | $116,253.99 |
| 83 | Statewide | Emergency Protective Measures | September 7, 2018 | $202,790.00 | $360,190.00 |
| 84 | Statewide | Emergency Protective Measures | January 21, 2025 | -$602.00 | $328,203.24 |
| 86 | Statewide | Emergency Protective Measures | March 28, 2018 | $116,899.10 | $124,299.10 |
| 87 | Statewide | Emergency Protective Measures | July 7, 2026 | -$59,661.50 | $129,934,154.93 |
| 90 | Statewide | Emergency Protective Measures | May 5, 2020 | $16,302.96 | $69,572,618.83 |
| 92 | Statewide | Emergency Protective Measures | August 19, 2024 | -$125,934.50 | $24,065.50 |
| 93 | Statewide | Emergency Protective Measures | June 8, 2020 | -$10,725.00 | $0.00 |
| 94 | Statewide | Emergency Protective Measures | April 5, 2018 | $235,763.50 | $244,263.50 |
| 96 | Statewide | Emergency Protective Measures | June 8, 2020 | -$10,725.00 | $0.00 |
| 97 | Statewide | Emergency Protective Measures | June 20, 2018 | $40,433.45 | $121,183.45 |
| 98 | Statewide | Emergency Protective Measures | December 29, 2017 | -$171,200,000.00 | $0.00 |
| 101 | Statewide | Debris Removal | February 15, 2023 | -$625.00 | $3,700.00 |
| 103 | Statewide | Emergency Protective Measures | May 2, 2018 | $65,064.00 | $102,564.00 |
| 104 | Unavailable | Debris Removal | August 24, 2026 | -$120,120.62 | $3,412,208.25 |
| 108 | Unavailable | Emergency Protective Measures | January 10, 2023 | -$33,056.93 | $410,671.25 |
| 110 | Unavailable | Emergency Protective Measures | August 12, 2026 | -$2,474.57 | $7,914,944.25 |
| 111 | Unavailable | Debris Removal | October 27, 2025 | -$196,974.67 | $15,075,454.36 |
| 113 | Unavailable | Debris Removal | May 13, 2025 | -$1,314,608.46 | $2,937,385.75 |
| 117 | Unavailable | Emergency Protective Measures | March 23, 2018 | $66,003.67 | $628,503.67 |
| 121 | Statewide | Emergency Protective Measures | November 6, 2019 | -$7,400.00 | $0.00 |
| 122 | Statewide | Emergency Protective Measures | August 12, 2025 | -$232,163.55 | $5,533,953.82 |
| 123 | Unavailable | Debris Removal | April 22, 2026 | -$376,573.73 | $11,128,498.79 |
| 124 | Unavailable | Debris Removal | November 18, 2024 | -$1,401,813.41 | $4,189,064.12 |
| 126 | Unavailable | Emergency Protective Measures | November 25, 2025 | -$99,867.27 | $4,983,594.47 |
| 127 | Unavailable | Debris Removal | September 11, 2023 | -$214,709.97 | $3,707,697.81 |
| 129 | Statewide | Emergency Protective Measures | January 13, 2026 | -$19,376.84 | $1,225,492.04 |
| 131 | Unavailable | Debris Removal | May 20, 2019 | $716,496.56 | $6,364,818.52 |
| 132 | Unavailable | Debris Removal | May 8, 2018 | $40,760.74 | $209,951.25 |
| 133 | Unavailable | Debris Removal | September 23, 2026 | -$3,976.46 | $1,691,193.74 |
| 134 | Unavailable | Debris Removal | March 31, 2025 | -$31,080.20 | $1,107,958.88 |
| 136 | Unavailable | Debris Removal | May 12, 2026 | -$265,365.36 | $2,486,393.33 |
| 137 | Unavailable | Debris Removal | May 12, 2026 | -$208,724.00 | $1,920,246.71 |
| 139 | Unavailable | Debris Removal | July 20, 2026 | -$85,853.80 | $4,897,563.09 |
| 140 | Unavailable | Debris Removal | January 13, 2026 | -$290,293.39 | $1,532,816.09 |
| 141 | Unavailable | Debris Removal | November 17, 2025 | -$133,410.42 | $3,472,498.26 |
| 142 | Unavailable | Debris Removal | March 24, 2021 | $44,761.66 | $7,657,738.71 |
| 146 | Unavailable | Emergency Protective Measures | April 2, 2025 | $4,317.87 | $906,430.88 |
| 147 | Unavailable | Debris Removal | January 17, 2023 | -$56,386.25 | $1,587,882.71 |
| 149 | Unavailable | Emergency Protective Measures | August 13, 2026 | -$386,127.47 | $1,039,536.30 |
| 150 | Unavailable | Debris Removal | October 10, 2024 | $1,755.50 | $558,580.50 |
| 151 | Unavailable | Debris Removal | September 27, 2022 | $742,684.88 | $5,011,086.45 |
| 152 | Unavailable | Emergency Protective Measures | March 19, 2025 | -$455,642.89 | $698,287.22 |
| 153 | Unavailable | Debris Removal | December 3, 2024 | -$1,260,509.91 | $5,184,900.23 |
| 154 | Unavailable | Debris Removal | April 10, 2025 | -$970.13 | $1,883,289.15 |
| 156 | Unavailable | Emergency Protective Measures | March 31, 2025 | -$924,926.28 | $6,828,744.96 |
| 157 | Unavailable | Debris Removal | April 2, 2025 | $335,912.15 | $4,640,478.67 |
| 158 | Unavailable | Debris Removal | October 15, 2025 | $14,410.75 | $1,883,403.57 |
| 159 | Unavailable | Debris Removal | April 4, 2025 | -$282,478.45 | $5,557,412.97 |
| 161 | Unavailable | Debris Removal | October 16, 2023 | -$169,910.22 | $9,254,871.93 |
| 162 | Unavailable | Debris Removal | March 23, 2018 | $2,249.30 | $6,982.54 |
| 166 | Unavailable | Emergency Protective Measures | April 17, 2025 | $211,155.07 | $2,656,305.23 |
| 168 | Unavailable | Debris Removal | October 4, 2024 | -$596,089.52 | $1,998,138.53 |
| 170 | Unavailable | Emergency Protective Measures | August 13, 2026 | -$598,034.72 | $718,707.85 |
| 174 | Statewide | Emergency Protective Measures | September 21, 2018 | $153,743.81 | $7,552,025.43 |
| 175 | Statewide | Debris Removal | June 12, 2026 | $1,043,939.66 | $18,525,546.47 |
| 177 | Statewide | Emergency Protective Measures | August 13, 2024 | -$839.65 | $958,055.15 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity