DR-4344 · California
WILDFIRES
Fire · Declared October 10, 2017
Recorded incident start October 8, 2017. Recorded incident end October 31, 2017. Declaration request October 9, 2017.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Butte County, California | IHP · Public Assistance · Hazard Mitigation | December 11, 2017 |
| Lake County, California | IHP · Public Assistance · Hazard Mitigation | December 11, 2017 |
| Mendocino County, California | IHP · Public Assistance · Hazard Mitigation | December 11, 2017 |
| Napa County, California | IHP · Public Assistance · Hazard Mitigation | December 11, 2017 |
| Nevada County, California | IHP · Public Assistance · Hazard Mitigation | December 11, 2017 |
| Orange County, California | IHP · Public Assistance · Hazard Mitigation | December 11, 2017 |
| Solano County, California | Public Assistance · Hazard Mitigation | December 11, 2017 |
| Sonoma County, California | IHP · Public Assistance · Hazard Mitigation | December 11, 2017 |
| Yuba County, California | IHP · Public Assistance · Hazard Mitigation | December 11, 2017 |
Public Assistance for this declaration
- Project worksheets
- 316
- Federal share obligated
- $485,632,272.25
- Median days to first recorded obligation
- 309
Timing uses 316 dated worksheets and starts on the original declaration date. Earliest first obligation January 27, 2018. Most recent obligation in the project snapshot October 15, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Emergency Protective Measures | 117 | $257,997,999.55 |
| Debris Removal | 31 | $179,291,079.16 |
| Parks, Recreational Facilities, and Other Items | 23 | $15,486,612.95 |
| Utilities | 30 | $15,271,110.77 |
| Management Costs | 48 | $6,947,283.84 |
| Roads and Bridges | 31 | $6,265,158.45 |
| Buildings and Equipment | 32 | $4,212,627.23 |
| Water Control Facilities | 4 | $160,400.30 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2018 | 263 |
| 2019 | 36 |
| 2020 | 12 |
| 2021 | 3 |
| 2023 | 1 |
| 2024 | 1 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Sonoma County, California | 95 | $57,329,929.45 |
| Napa County, California | 41 | $6,642,391.97 |
| Mendocino County, California | 38 | $4,343,649.26 |
| Orange County, California | 12 | $2,581,773.88 |
| Yuba County, California | 12 | $1,139,916.87 |
| Solano County, California | 9 | $823,071.06 |
| Lake County, California | 12 | $314,834.80 |
| Nevada County, California | 2 | $136,309.19 |
| Butte County, California | 1 | $106,138.00 |
Projects FEMA labels statewide
- Project worksheets
- 88
- Federal share obligated
- $411,215,334.92
- Median days to first recorded obligation
- 324
Timing uses 88 dated worksheets and starts on the original declaration date. Earliest first obligation January 27, 2018. Most recent obligation in the project snapshot October 15, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Emergency Protective Measures | 26 | $226,960,164.49 |
| Debris Removal | 7 | $168,700,042.50 |
| Parks, Recreational Facilities, and Other Items | 14 | $8,134,161.85 |
| Management Costs | 20 | $4,226,149.45 |
| Buildings and Equipment | 12 | $2,779,453.19 |
| Roads and Bridges | 6 | $362,136.43 |
| Water Control Facilities | 2 | $53,227.01 |
| Utilities | 1 | $0.00 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2018 | 74 |
| 2019 | 5 |
| 2020 | 7 |
| 2023 | 1 |
| 2024 | 1 |
Project worksheet revisions
75 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 2 | February 18, 2021 | -$10,030,318.88 | $147,379,681.12 |
| Worksheet 263 | August 30, 2022 | -$2,332,705.90 | $0.00 |
| Worksheet 7 | August 19, 2025 | $2,098,374.50 | $8,395,569.78 |
| Worksheet 325 | July 24, 2023 | $2,051,135.50 | $6,225,150.73 |
| Worksheet 291 | May 4, 2022 | -$1,196,025.00 | $0.00 |
| Worksheet 279 | December 1, 2021 | $573,603.30 | $1,486,068.61 |
| Worksheet 216 | January 14, 2021 | $536,987.45 | $597,750.00 |
| Worksheet 209 | December 5, 2023 | -$486,577.50 | $0.00 |
| Worksheet 159 | February 3, 2023 | -$366,521.89 | $546,225.94 |
| Worksheet 90 | June 10, 2022 | $355,593.27 | $5,668,071.39 |
| Worksheet 80 | June 7, 2022 | -$350,744.36 | $543,693.25 |
| Worksheet 149 | May 6, 2026 | -$349,325.50 | $465,048.69 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity