DR-4356 · Vermont
SEVERE STORM AND FLOODING
Severe Storm · Declared January 2, 2018
Recorded incident start October 29, 2017. Recorded incident end October 30, 2017. Declaration request November 28, 2017. Recorded closeout September 12, 2023.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Addison County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Chittenden County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Essex County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Franklin County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Grand Isle County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Lamoille County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Orange County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Orleans County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Washington County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
| Windham County, Vermont | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 99
- Federal share obligated
- $5,126,898.02
- Median days to first recorded obligation
- 190
Timing uses 99 dated worksheets and starts on the original declaration date. Earliest first obligation May 7, 2018. Most recent obligation in the project snapshot January 14, 2022.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 6 | $2,547,012.48 |
| Roads and Bridges | 12 | $1,029,289.61 |
| Debris Removal | 30 | $937,416.89 |
| Management Costs | 38 | $420,205.70 |
| Emergency Protective Measures | 10 | $98,216.73 |
| Buildings and Equipment | 1 | $54,035.36 |
| Parks, Recreational Facilities, and Other Items | 2 | $40,721.25 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2018 | 99 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Lamoille County, Vermont | 14 | $2,569,800.26 |
| Windham County, Vermont | 18 | $1,075,219.83 |
| Washington County, Vermont | 17 | $797,556.42 |
| Franklin County, Vermont | 13 | $149,230.33 |
| Chittenden County, Vermont | 16 | $141,546.49 |
| Addison County, Vermont | 11 | $69,643.10 |
| Orange County, Vermont | 4 | $22,236.60 |
| Orleans County, Vermont | 2 | $3,465.90 |
Projects FEMA labels statewide
- Project worksheets
- 4
- Federal share obligated
- $298,199.09
- Median days to first recorded obligation
- 183.5
Timing uses 4 dated worksheets and starts on the original declaration date. Earliest first obligation June 5, 2018. Most recent obligation in the project snapshot January 14, 2022.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Management Costs | 2 | $263,731.68 |
| Debris Removal | 1 | $17,715.80 |
| Emergency Protective Measures | 1 | $16,751.61 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2018 | 4 |
Project worksheet revisions
42 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 30 | January 14, 2022 | -$169,854.55 | $262,550.63 |
| Worksheet 64 | February 22, 2021 | $65,926.80 | $1,809,802.85 |
| Worksheet 84 | November 2, 2020 | -$53,428.76 | $46,866.09 |
| Worksheet 92 | October 27, 2020 | -$16,416.25 | $9,222.80 |
| Worksheet 99 | October 26, 2020 | -$9,191.27 | $702.02 |
| Worksheet 79 | June 27, 2019 | -$6,790.30 | $4,816.64 |
| Worksheet 98 | July 9, 2019 | $6,569.80 | $26,279.22 |
| Worksheet 97 | March 12, 2020 | $5,241.28 | $5,241.28 |
| Worksheet 96 | April 23, 2019 | $4,910.18 | $19,640.73 |
| Worksheet 91 | March 18, 2020 | $4,087.50 | $192,525.00 |
| Worksheet 87 | July 20, 2020 | $3,476.78 | $390,370.82 |
| Worksheet 54 | October 26, 2018 | $2,452.77 | $47,556.17 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity