DR-4367 · Maine
SEVERE STORM AND FLOODING
Coastal Storm · Declared May 30, 2018
Recorded incident start March 2, 2018. Recorded incident end March 8, 2018. Declaration request March 30, 2018.
Other designated areas
| Area listed | Programs listed |
|---|---|
| York (County)(in MSA 6400,6450) | Public Assistance · Hazard Mitigation |
Public Assistance for this declaration
- Project worksheets
- 65
- Federal share obligated
- $10,722,274.01
- Median days to first recorded obligation
- 314
Timing uses 65 dated worksheets and starts on the original declaration date. Earliest first obligation October 16, 2018. Most recent obligation in the project snapshot May 26, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Parks, Recreational Facilities, and Other Items | 37 | $9,471,477.69 |
| Roads and Bridges | 11 | $653,325.04 |
| Management Costs | 8 | $304,270.42 |
| Emergency Protective Measures | 8 | $243,268.83 |
| Water Control Facilities | 1 | $49,932.03 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2018 | 9 |
| 2019 | 42 |
| 2020 | 5 |
| 2021 | 3 |
| 2022 | 3 |
| 2025 | 1 |
| 2026 | 2 |
Projects FEMA labels statewide
- Project worksheets
- 1
- Federal share obligated
- $124,185.00
- Median days to first recorded obligation
- 139
Timing uses 1 dated worksheets and starts on the original declaration date. Earliest first obligation October 16, 2018. Most recent obligation in the project snapshot June 3, 2019.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Management Costs | 1 | $124,185.00 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2018 | 1 |
Project worksheet revisions
11 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 64 | September 21, 2022 | -$650,487.92 | $251,516.04 |
| Worksheet 7 | June 21, 2021 | -$260,764.60 | $261,951.65 |
| Worksheet 47 | May 26, 2026 | -$144,139.84 | $321,137.66 |
| Worksheet 36 | November 24, 2021 | $130,389.00 | $427,881.00 |
| Worksheet 6 | June 3, 2019 | $112,612.00 | $124,185.00 |
| Worksheet 24 | July 22, 2024 | $102,485.21 | $255,862.50 |
| Worksheet 38 | November 24, 2021 | $56,523.75 | $871,428.75 |
| Worksheet 67 | December 3, 2025 | -$41,062.50 | $0.00 |
| Worksheet 57 | February 13, 2020 | -$15,990.89 | $5,228.67 |
| Worksheet 33 | February 16, 2023 | -$6,114.95 | $0.00 |
| Worksheet 40 | February 2, 2023 | -$870.17 | $0.00 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.