DR-4395 · Hawaii
HURRICANE LANE
Hurricane · Declared September 27, 2018
Recorded incident start August 22, 2018. Recorded incident end August 29, 2018. Declaration request September 6, 2018.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Hawaii County, Hawaii | Public Assistance · Hazard Mitigation | Unavailable |
| Kauai County, Hawaii | Public Assistance · Hazard Mitigation | Unavailable |
| Maui County, Hawaii | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 73
- Federal share obligated
- $18,041,703.32
- Median days to first recorded obligation
- 410
Timing uses 73 dated worksheets and starts on the original declaration date. Earliest first obligation January 25, 2019. Most recent obligation in the project snapshot October 30, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 24 | $13,725,357.17 |
| Management Costs | 13 | $1,944,477.87 |
| Emergency Protective Measures | 17 | $1,324,374.39 |
| Utilities | 4 | $540,077.09 |
| Parks, Recreational Facilities, and Other Items | 5 | $381,746.65 |
| Debris Removal | 8 | $103,335.90 |
| Buildings and Equipment | 2 | $22,334.25 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2019 | 42 |
| 2020 | 24 |
| 2022 | 3 |
| 2023 | 4 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Hawaii County, Hawaii | 39 | $15,012,227.77 |
| Maui County, Hawaii | 7 | $1,043,297.43 |
| Kauai County, Hawaii | 20 | $374,792.97 |
Projects FEMA labels statewide
- Project worksheets
- 7
- Federal share obligated
- $1,611,385.15
- Median days to first recorded obligation
- 245
Timing uses 7 dated worksheets and starts on the original declaration date. Earliest first obligation January 25, 2019. Most recent obligation in the project snapshot January 12, 2023.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Management Costs | 2 | $998,973.56 |
| Emergency Protective Measures | 3 | $311,183.84 |
| Roads and Bridges | 1 | $298,640.25 |
| Debris Removal | 1 | $2,587.50 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2019 | 4 |
| 2020 | 2 |
| 2023 | 1 |
Project worksheet revisions
24 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 54 | July 21, 2022 | $793,434.20 | $953,952.88 |
| Worksheet 8 | February 24, 2021 | -$724,303.80 | $0.00 |
| Worksheet 45 | February 26, 2026 | $515,699.98 | $608,425.88 |
| Worksheet 65 | November 18, 2020 | $409,457.30 | $998,552.06 |
| Worksheet 11 | December 5, 2022 | -$357,185.40 | $0.00 |
| Worksheet 16 | April 8, 2021 | $294,905.25 | $298,640.25 |
| Worksheet 23 | April 22, 2021 | -$292,283.27 | $680,838.92 |
| Worksheet 62 | September 24, 2026 | -$212,650.44 | $982,439.31 |
| Worksheet 4 | February 24, 2021 | -$143,637.26 | $0.00 |
| Worksheet 35 | November 29, 2022 | $112,153.07 | $131,353.50 |
| Worksheet 76 | December 5, 2022 | -$87,903.58 | $0.00 |
| Worksheet 25 | February 24, 2021 | -$80,083.97 | $0.00 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.