DR-4425 · California
SEVERE STORMS AND FLOODING
Severe Storm · Declared April 8, 2019
Recorded incident start February 14, 2019. Recorded incident end February 15, 2019. Declaration request March 28, 2019.
Other designated areas
| Area listed | Programs listed |
|---|---|
| Soboba Indian Reservation | Public Assistance · Hazard Mitigation |
Public Assistance for this declaration
- Project worksheets
- 4
- Federal share obligated
- $5,460,572.79
- Median days to first recorded obligation
- 985
Timing uses 4 dated worksheets and starts on the original declaration date. Earliest first obligation June 18, 2020. Most recent obligation in the project snapshot March 2, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Water Control Facilities | 1 | $4,863,360.75 |
| Debris Removal | 1 | $389,168.21 |
| Emergency Protective Measures | 1 | $105,506.28 |
| Roads and Bridges | 1 | $102,537.55 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2020 | 1 |
| 2021 | 1 |
| 2022 | 1 |
| 2026 | 1 |
Projects FEMA labels statewide
- Project worksheets
- 4
- Federal share obligated
- $5,460,572.79
- Median days to first recorded obligation
- 985
Timing uses 4 dated worksheets and starts on the original declaration date. Earliest first obligation June 18, 2020. Most recent obligation in the project snapshot March 2, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Water Control Facilities | 1 | $4,863,360.75 |
| Debris Removal | 1 | $389,168.21 |
| Emergency Protective Measures | 1 | $105,506.28 |
| Roads and Bridges | 1 | $102,537.55 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2020 | 1 |
| 2021 | 1 |
| 2022 | 1 |
| 2026 | 1 |
Project worksheet revisions
3 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 6 | September 11, 2025 | $64,861.37 | $389,168.21 |
| Worksheet 1 | September 11, 2025 | $17,584.38 | $105,506.28 |
| Worksheet 4 | September 11, 2025 | $17,089.59 | $102,537.55 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.