DR-4441 · Arkansas
SEVERE STORMS AND FLOODING
Flood · Declared June 8, 2019
Recorded incident start May 21, 2019. Recorded incident end June 14, 2019. Declaration request June 6, 2019.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Arkansas County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Chicot County, Arkansas | Public Assistance · Hazard Mitigation | August 7, 2019 |
| Conway County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Crawford County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Desha County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Faulkner County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Franklin County, Arkansas | Public Assistance · Hazard Mitigation | August 7, 2019 |
| Jefferson County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Johnson County, Arkansas | Public Assistance · Hazard Mitigation | August 7, 2019 |
| Lincoln County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Logan County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Perry County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Pope County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Pulaski County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Searcy County, Arkansas | Public Assistance | August 7, 2019 |
| Sebastian County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
| Yell County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 7, 2019 |
Public Assistance for this declaration
- Project worksheets
- 344
- Federal share obligated
- $53,497,957.57
- Median days to first recorded obligation
- 269
Timing uses 344 dated worksheets and starts on the original declaration date. Earliest first obligation August 6, 2019. Most recent obligation in the project snapshot August 26, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 37 | $24,707,450.49 |
| Emergency Protective Measures | 83 | $6,642,565.88 |
| Management Costs | 53 | $6,311,446.76 |
| Roads and Bridges | 69 | $4,470,669.70 |
| Buildings and Equipment | 21 | $3,725,138.73 |
| Parks, Recreational Facilities, and Other Items | 44 | $3,711,920.18 |
| Debris Removal | 26 | $3,520,526.60 |
| Water Control Facilities | 11 | $408,239.23 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2019 | 101 |
| 2020 | 227 |
| 2021 | 13 |
| 2022 | 1 |
| 2023 | 2 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Pulaski County, Arkansas | 81 | $20,837,320.89 |
| Sebastian County, Arkansas | 45 | $16,929,355.33 |
| Crawford County, Arkansas | 39 | $1,567,987.84 |
| Faulkner County, Arkansas | 20 | $1,565,860.57 |
| Logan County, Arkansas | 14 | $1,074,250.66 |
| Jefferson County, Arkansas | 34 | $1,072,351.06 |
| Perry County, Arkansas | 14 | $977,668.03 |
| Yell County, Arkansas | 16 | $842,829.95 |
| Desha County, Arkansas | 7 | $742,400.38 |
| Searcy County, Arkansas | 12 | $651,084.18 |
| Conway County, Arkansas | 11 | $605,664.68 |
| Franklin County, Arkansas | 11 | $502,284.79 |
Projects FEMA labels statewide
- Project worksheets
- 37
- Federal share obligated
- $6,021,720.55
- Median days to first recorded obligation
- 248
Timing uses 37 dated worksheets and starts on the original declaration date. Earliest first obligation August 6, 2019. Most recent obligation in the project snapshot January 26, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Management Costs | 7 | $3,789,618.99 |
| Emergency Protective Measures | 14 | $1,352,823.45 |
| Parks, Recreational Facilities, and Other Items | 5 | $345,384.68 |
| Roads and Bridges | 4 | $281,153.67 |
| Buildings and Equipment | 2 | $129,776.54 |
| Debris Removal | 3 | $76,033.45 |
| Water Control Facilities | 1 | $29,560.26 |
| Utilities | 1 | $17,369.51 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2019 | 12 |
| 2020 | 25 |
Project worksheet revisions
59 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 166 | September 1, 2022 | -$2,853,217.92 | $2,231,782.08 |
| Worksheet 311 | April 15, 2026 | -$1,771,012.79 | $2,919,923.22 |
| Worksheet 1 | July 28, 2021 | $1,404,279.11 | $3,702,818.30 |
| Worksheet 305 | February 16, 2024 | $1,298,293.10 | $5,280,579.80 |
| Worksheet 201 | March 30, 2023 | -$1,266,504.75 | $0.00 |
| Worksheet 200 | September 1, 2021 | -$955,251.74 | $740,444.26 |
| Worksheet 285 | November 8, 2021 | -$942,239.03 | $1,228,731.33 |
| Worksheet 299 | October 4, 2021 | $588,475.70 | $705,772.51 |
| Worksheet 328 | January 26, 2026 | $478,027.20 | $847,271.16 |
| Worksheet 102 | January 4, 2023 | -$449,396.27 | $140,646.00 |
| Worksheet 187 | March 10, 2025 | -$274,069.98 | $200,554.02 |
| Worksheet 197 | September 1, 2021 | -$174,167.96 | $392,198.48 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity