DR-4443 · Idaho
SEVERE STORMS, FLOODING, LANDSLIDES, AND MUDSLIDES
Flood · Declared June 12, 2019
Recorded incident start April 7, 2019. Recorded incident end April 13, 2019. Declaration request May 23, 2019.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Adams County, Idaho | Public Assistance · Hazard Mitigation | Unavailable |
| Idaho County, Idaho | Public Assistance · Hazard Mitigation | Unavailable |
| Latah County, Idaho | Public Assistance · Hazard Mitigation | Unavailable |
| Lewis County, Idaho | Public Assistance · Hazard Mitigation | Unavailable |
| Valley County, Idaho | Public Assistance · Hazard Mitigation | Unavailable |
Other designated areas
| Area listed | Programs listed |
|---|---|
| Nez Perce Indian Reservation | Public Assistance · Hazard Mitigation |
Public Assistance for this declaration
- Project worksheets
- 54
- Federal share obligated
- $4,399,025.87
- Median days to first recorded obligation
- 182
Timing uses 54 dated worksheets and starts on the original declaration date. Earliest first obligation September 4, 2019. Most recent obligation in the project snapshot May 27, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 19 | $3,944,519.88 |
| Management Costs | 13 | $238,859.38 |
| Emergency Protective Measures | 9 | $57,864.05 |
| Parks, Recreational Facilities, and Other Items | 4 | $52,001.36 |
| Debris Removal | 4 | $50,603.38 |
| Water Control Facilities | 2 | $35,547.75 |
| Utilities | 3 | $19,630.07 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2019 | 30 |
| 2020 | 9 |
| 2021 | 5 |
| 2022 | 7 |
| 2023 | 1 |
| 2024 | 2 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Idaho County, Idaho | 18 | $3,063,459.81 |
| Valley County, Idaho | 2 | $647,632.92 |
| Latah County, Idaho | 14 | $237,751.57 |
| Adams County, Idaho | 4 | $159,374.54 |
| Lewis County, Idaho | 4 | $67,907.99 |
Projects FEMA labels statewide
- Project worksheets
- 6
- Federal share obligated
- $195,684.77
- Median days to first recorded obligation
- 146
Timing uses 6 dated worksheets and starts on the original declaration date. Earliest first obligation September 4, 2019. Most recent obligation in the project snapshot December 11, 2019.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Management Costs | 3 | $166,070.84 |
| Water Control Facilities | 1 | $17,172.75 |
| Emergency Protective Measures | 1 | $7,493.02 |
| Debris Removal | 1 | $4,948.16 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2019 | 6 |
Project worksheet revisions
13 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 20 | September 8, 2020 | $677,465.25 | $758,105.25 |
| Worksheet 57 | December 15, 2023 | $578,721.86 | $607,155.86 |
| Worksheet 14 | June 8, 2023 | $341,596.26 | $604,906.22 |
| Worksheet 23 | February 16, 2023 | $164,990.39 | $701,713.64 |
| Worksheet 27 | June 8, 2023 | $164,179.11 | $469,060.49 |
| Worksheet 6 | January 8, 2020 | $71,336.25 | $82,586.25 |
| Worksheet 28 | February 13, 2023 | -$38,327.90 | $183,547.46 |
| Worksheet 26 | August 5, 2020 | $22,928.86 | $32,776.36 |
| Worksheet 30 | March 17, 2020 | $8,105.74 | $13,330.47 |
| Worksheet 55 | November 15, 2022 | $6,692.00 | $40,433.45 |
| Worksheet 15 | February 16, 2023 | $826.32 | $108,099.57 |
| Worksheet 25 | November 4, 2022 | $825.00 | $10,225.05 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity