DR-4451 · Missouri
Project worksheets 1238–1421
SEVERE STORMS, TORNADOES, AND FLOODING
Showing 301–393 of 393 worksheets with dated revisions, in worksheet number order.
Worksheet timelines
| Worksheet | Applicant location | Work category | Last activity date | Last signed change | Federal share in project snapshot |
|---|---|---|---|---|---|
| 1238 | Bates County, Missouri | Management Costs | December 1, 2023 | -$10,082.90 | $0.00 |
| 1239 | Howard County, Missouri | Management Costs | March 22, 2022 | -$16,230.64 | $0.00 |
| 1240 | Harrison County, Missouri | Management Costs | January 4, 2022 | -$2,108.95 | $0.00 |
| 1241 | Mercer County, Missouri | Management Costs | February 1, 2021 | -$3,940.93 | $0.00 |
| 1244 | Texas County, Missouri | Management Costs | February 10, 2023 | -$12,555.83 | $730.00 |
| 1245 | Livingston County, Missouri | Management Costs | January 4, 2022 | -$4,405.30 | $0.00 |
| 1247 | Mercer County, Missouri | Management Costs | June 14, 2023 | -$2,171.15 | $0.00 |
| 1249 | Chariton County, Missouri | Management Costs | January 17, 2024 | -$7,566.44 | $2,843.30 |
| 1250 | Bates County, Missouri | Management Costs | February 6, 2025 | -$1,546.26 | $12,950.50 |
| 1254 | Marion County, Missouri | Emergency Protective Measures | July 18, 2022 | -$202.50 | $139,276.32 |
| 1255 | Chariton County, Missouri | Management Costs | May 23, 2022 | -$183.84 | $12,453.47 |
| 1256 | Buchanan County, Missouri | Management Costs | August 3, 2026 | -$40,198.87 | $0.00 |
| 1258 | Lincoln County, Missouri | Management Costs | March 7, 2022 | -$9,251.32 | $5,715.00 |
| 1259 | Lincoln County, Missouri | Management Costs | March 9, 2022 | -$2,793.83 | $0.00 |
| 1262 | Saline County, Missouri | Management Costs | June 14, 2023 | -$9,241.20 | $0.00 |
| 1263 | Harrison County, Missouri | Management Costs | April 18, 2023 | -$4,188.74 | $0.00 |
| 1264 | Harrison County, Missouri | Management Costs | May 16, 2022 | -$1,802.47 | $1,715.78 |
| 1265 | Harrison County, Missouri | Management Costs | January 23, 2023 | -$4,389.03 | $485.95 |
| 1266 | Saline County, Missouri | Management Costs | May 3, 2023 | -$2,014.12 | $0.00 |
| 1267 | Harrison County, Missouri | Management Costs | August 8, 2022 | -$4,169.77 | $3,787.42 |
| 1269 | Putnam County, Missouri | Roads and Bridges | May 8, 2025 | -$4,294.95 | $0.00 |
| 1270 | Webster County, Missouri | Management Costs | October 12, 2021 | -$52,751.85 | $13,181.39 |
| 1272 | Cole County, Missouri | Parks, Recreational Facilities, and Other Items | December 8, 2023 | -$55,896.17 | $83,785.33 |
| 1274 | Statewide | Debris Removal | August 10, 2022 | -$465,313.35 | $0.00 |
| 1275 | Laclede County, Missouri | Management Costs | June 14, 2022 | -$7,371.11 | $0.00 |
| 1276 | Chariton County, Missouri | Emergency Protective Measures | May 5, 2022 | $15,249.24 | $111,314.18 |
| 1285 | Grundy County, Missouri | Management Costs | October 17, 2022 | -$23,958.63 | $0.00 |
| 1289 | Lincoln County, Missouri | Management Costs | October 3, 2022 | -$7,412.76 | $0.00 |
| 1296 | Jackson County, Missouri | Management Costs | November 21, 2025 | -$24,732.54 | $0.00 |
| 1300 | Statewide | Buildings and Equipment | March 22, 2023 | -$34,413.69 | $98,326.37 |
| 1301 | Chariton County, Missouri | Management Costs | February 10, 2023 | $3,357.43 | $23,623.04 |
| 1304 | Putnam County, Missouri | Management Costs | April 20, 2026 | -$10,419.42 | $0.00 |
| 1309 | Shelby County, Missouri | Management Costs | June 2, 2021 | -$7,657.57 | $2,318.03 |
| 1313 | St. Charles County, Missouri | Management Costs | September 1, 2021 | -$3,934.27 | $0.00 |
| 1314 | Cole County, Missouri | Parks, Recreational Facilities, and Other Items | July 20, 2023 | -$131,978.04 | $28,492.71 |
| 1315 | Grundy County, Missouri | Management Costs | January 4, 2022 | -$2,546.25 | $0.00 |
| 1318 | Carroll County, Missouri | Management Costs | March 5, 2024 | -$10,597.69 | $314.67 |
| 1319 | Statewide | Management Costs | August 3, 2022 | -$8,849.34 | $0.00 |
| 1320 | Cole County, Missouri | Parks, Recreational Facilities, and Other Items | October 7, 2022 | -$55,993.37 | $0.00 |
| 1321 | Putnam County, Missouri | Management Costs | September 30, 2026 | -$9,910.95 | $0.00 |
| 1323 | Lewis County, Missouri | Management Costs | July 11, 2023 | -$7,496.82 | $0.00 |
| 1324 | Sullivan County, Missouri | Management Costs | October 17, 2022 | -$179.18 | $251.14 |
| 1326 | Lincoln County, Missouri | Management Costs | August 3, 2021 | -$4,642.07 | $2,919.68 |
| 1331 | McDonald County, Missouri | Management Costs | September 1, 2022 | -$8,704.67 | $123.36 |
| 1332 | St. Charles County, Missouri | Water Control Facilities | April 22, 2021 | -$258.15 | $17,585.72 |
| 1334 | Andrew County, Missouri | Management Costs | August 3, 2022 | -$3,698.60 | $0.00 |
| 1335 | Clark County, Missouri | Management Costs | March 9, 2022 | -$16,206.86 | $0.00 |
| 1336 | Boone County, Missouri | Management Costs | April 15, 2026 | -$6,049.40 | $0.00 |
| 1338 | Livingston County, Missouri | Management Costs | August 3, 2022 | -$615.96 | $0.00 |
| 1339 | St. Charles County, Missouri | Utilities | August 1, 2023 | $63,559.50 | $179,065.29 |
| 1341 | Bollinger County, Missouri | Management Costs | January 9, 2023 | -$9,159.75 | $0.00 |
| 1347 | Mercer County, Missouri | Management Costs | July 22, 2021 | -$8,379.56 | $10,917.74 |
| 1348 | St. Charles County, Missouri | Management Costs | June 2, 2021 | -$4,608.68 | $0.00 |
| 1350 | Cedar County, Missouri | Management Costs | August 1, 2023 | -$10,101.20 | $6,745.70 |
| 1351 | Boone County, Missouri | Management Costs | December 1, 2021 | -$6,075.53 | $7,594.98 |
| 1353 | Lincoln County, Missouri | Management Costs | March 22, 2023 | -$4,678.62 | $1,533.76 |
| 1357 | Mercer County, Missouri | Management Costs | August 1, 2023 | -$4,377.77 | $0.00 |
| 1358 | Camden County, Missouri | Management Costs | January 17, 2024 | -$3,682.50 | $94,644.00 |
| 1360 | Barton County, Missouri | Management Costs | April 15, 2026 | -$7,887.09 | $0.00 |
| 1361 | Miller County, Missouri | Management Costs | April 4, 2024 | -$24,994.35 | $26,352.07 |
| 1363 | Lincoln County, Missouri | Management Costs | May 3, 2021 | -$26.57 | $405.00 |
| 1364 | Chariton County, Missouri | Management Costs | May 3, 2021 | -$4,530.27 | $2,463.00 |
| 1368 | St. Charles County, Missouri | Management Costs | August 9, 2021 | -$7,499.18 | $0.00 |
| 1369 | Vernon County, Missouri | Management Costs | February 2, 2022 | -$601.00 | $1,340.00 |
| 1372 | Daviess County, Missouri | Management Costs | February 10, 2023 | -$30,990.02 | $0.00 |
| 1373 | Macon County, Missouri | Management Costs | April 4, 2024 | -$19,473.57 | $4,445.00 |
| 1374 | Sullivan County, Missouri | Management Costs | January 19, 2024 | -$7,382.41 | $0.00 |
| 1375 | New Madrid County, Missouri | Management Costs | May 12, 2022 | -$8,230.60 | $4,519.89 |
| 1377 | Randolph County, Missouri | Management Costs | May 23, 2022 | -$1,467.66 | $0.00 |
| 1379 | McDonald County, Missouri | Roads and Bridges | June 5, 2023 | -$14,009.03 | $172,587.33 |
| 1383 | Nodaway County, Missouri | Management Costs | May 6, 2022 | -$1,261.85 | $4,213.12 |
| 1384 | Cole County, Missouri | Management Costs | January 17, 2024 | -$134,615.14 | $29,756.95 |
| 1385 | Marion County, Missouri | Roads and Bridges | July 1, 2022 | -$5,516.52 | $215,469.71 |
| 1386 | Ralls County, Missouri | Roads and Bridges | March 1, 2022 | -$5,036.48 | $253,343.18 |
| 1388 | Putnam County, Missouri | Management Costs | August 7, 2023 | -$5,707.51 | $2,499.25 |
| 1394 | Grundy County, Missouri | Management Costs | January 4, 2022 | -$6,216.10 | $1,294.77 |
| 1395 | Marion County, Missouri | Management Costs | January 23, 2023 | -$16,781.71 | $0.00 |
| 1396 | McDonald County, Missouri | Management Costs | June 16, 2023 | -$17,501.20 | $7,162.02 |
| 1397 | Holt County, Missouri | Management Costs | April 18, 2022 | -$12,420.85 | $4,752.00 |
| 1399 | Vernon County, Missouri | Management Costs | October 6, 2022 | -$2,997.44 | $0.00 |
| 1400 | Marion County, Missouri | Management Costs | May 2, 2022 | -$7,148.52 | $0.00 |
| 1401 | Marion County, Missouri | Management Costs | September 19, 2023 | -$18,395.27 | $0.00 |
| 1402 | Adair County, Missouri | Management Costs | August 1, 2023 | -$4,804.73 | $0.00 |
| 1403 | Cole County, Missouri | Management Costs | September 1, 2023 | -$7,517.31 | $97,832.84 |
| 1405 | Nodaway County, Missouri | Roads and Bridges | January 13, 2022 | -$17,590.47 | $94,861.28 |
| 1408 | Holt County, Missouri | Management Costs | September 18, 2026 | -$179,126.35 | $0.00 |
| 1409 | Pike County, Missouri | Management Costs | May 7, 2024 | -$10,398.58 | $1,348.56 |
| 1411 | Callaway County, Missouri | Management Costs | May 16, 2022 | -$4,456.82 | $0.00 |
| 1414 | St. Charles County, Missouri | Parks, Recreational Facilities, and Other Items | October 23, 2023 | $10,159.84 | $110,923.03 |
| 1415 | Adair County, Missouri | Roads and Bridges | March 27, 2023 | $107,410.25 | $409,204.66 |
| 1417 | Adair County, Missouri | Management Costs | August 1, 2023 | $4,368.37 | $38,876.58 |
| 1419 | St. Charles County, Missouri | Management Costs | January 23, 2023 | -$83,407.44 | $0.00 |
| 1421 | Cole County, Missouri | Parks, Recreational Facilities, and Other Items | August 9, 2021 | -$8,328.14 | $0.00 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity