DR-4465 · North Carolina

Pender County, North Carolina

HURRICANE DORIAN · Declared October 4, 2019

Programs listed for this county · Public Assistance · Hazard Mitigation

Official FEMA disaster page · Other declarations for this county

Public Assistance for applicants listed in this county

Project worksheets
14
Federal share obligated
$2,734,626.12
Median days to first recorded obligation
189.5

Timing uses 14 dated worksheets and starts on the original declaration date. Earliest first obligation February 5, 2020. Most recent obligation in the project snapshot June 11, 2024.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Parks, Recreational Facilities, and Other Items1$1,913,659.22
Utilities2$504,678.74
Emergency Protective Measures6$309,116.82
Management Costs5$7,171.34
First obligations by year
Year of first recorded obligation
YearWorksheets
202014

Revisions for worksheets with applicants in this county

5 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 432June 11, 2024-$130,963.50$0.00
Worksheet 400March 26, 2024-$30,430.28$3,602.72
Worksheet 410June 11, 2024-$10,626.16$0.00
Worksheet 86February 8, 2022-$9,264.66$1,913,659.22
Worksheet 390April 2, 2024-$1,167.17$0.00

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.