DR-4470 · Mississippi

Alcorn County, Mississippi

SEVERE STORM, STRAIGHT-LINE WINDS, AND FLOODING · Declared December 6, 2019

Programs listed for this county · Public Assistance · Hazard Mitigation

Official FEMA disaster page · Other declarations for this county

Public Assistance for applicants listed in this county

Project worksheets
31
Federal share obligated
$5,703,527.46
Median days to first recorded obligation
202

Timing uses 31 dated worksheets and starts on the original declaration date. Earliest first obligation April 2, 2020. Most recent obligation in the project snapshot April 2, 2024.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Debris Removal3$2,044,115.15
Water Control Facilities1$1,758,335.09
Utilities4$1,338,801.50
Parks, Recreational Facilities, and Other Items3$170,251.67
Emergency Protective Measures6$121,040.26
Management Costs6$119,133.87
Roads and Bridges2$81,944.14
Buildings and Equipment6$69,905.78
First obligations by year
Year of first recorded obligation
YearWorksheets
202027
20214

Revisions for worksheets with applicants in this county

5 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 105May 10, 2021-$288,126.50$1,977,741.81
Worksheet 102April 2, 2024$273,335.09$1,758,335.09
Worksheet 127March 26, 2024-$248,738.22$10,118.11
Worksheet 101February 15, 2023-$26,584.88$90,081.42
Worksheet 91June 14, 2021-$5,993.78$1,298.37

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.