DR-4567 · New York
Putnam County, New York
TROPICAL STORM ISAIAS · Declared October 2, 2020
Programs listed for this county · Public Assistance · Hazard Mitigation
Official FEMA disaster page · Other declarations for this county
Public Assistance for applicants listed in this county
- Project worksheets
- 25
- Federal share obligated
- $1,482,171.50
- Median days to first recorded obligation
- 550
Timing uses 25 dated worksheets and starts on the original declaration date. Earliest first obligation July 2, 2021. Most recent obligation in the project snapshot July 1, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Debris Removal | 11 | $1,232,511.86 |
| Emergency Protective Measures | 5 | $127,611.05 |
| Utilities | 1 | $53,339.18 |
| Management Costs | 7 | $47,864.97 |
| Parks, Recreational Facilities, and Other Items | 1 | $20,844.44 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2021 | 4 |
| 2022 | 18 |
| 2023 | 3 |
Revisions for worksheets with applicants in this county
10 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 297 | April 8, 2022 | $19,278.13 | $115,668.77 |
| Worksheet 314 | April 8, 2022 | $16,318.13 | $97,908.79 |
| Worksheet 293 | April 8, 2022 | $8,306.24 | $49,837.47 |
| Worksheet 572 | July 1, 2026 | -$6,817.06 | $8,754.96 |
| Worksheet 268 | April 8, 2022 | $4,295.07 | $25,770.38 |
| Worksheet 321 | April 8, 2022 | $3,474.07 | $20,844.44 |
| Worksheet 506 | November 24, 2025 | -$2,887.48 | $0.00 |
| Worksheet 97 | April 8, 2022 | $1,021.41 | $6,128.47 |
| Worksheet 148 | April 8, 2022 | $890.39 | $5,342.32 |
| Worksheet 160 | April 8, 2022 | $786.64 | $4,719.84 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.