DR-4575 · Oklahoma

Comanche County, Oklahoma

SEVERE WINTER STORM · Declared December 21, 2020

Programs listed for this county · Public Assistance · Hazard Mitigation

Official FEMA disaster page · Other declarations for this county

Public Assistance for applicants listed in this county

Project worksheets
17
Federal share obligated
$699,720.28
Median days to first recorded obligation
228

Timing uses 17 dated worksheets and starts on the original declaration date. Earliest first obligation April 14, 2021. Most recent obligation in the project snapshot January 6, 2026.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Debris Removal6$653,513.73
Emergency Protective Measures6$30,543.21
Management Costs4$8,212.78
Utilities1$7,450.56
First obligations by year
Year of first recorded obligation
YearWorksheets
202112
20225

Revisions for worksheets with applicants in this county

14 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 64July 12, 2022$45,094.25$270,565.48
Worksheet 274October 6, 2025-$15,743.00$0.00
Worksheet 88January 27, 2022-$13,342.03$6,990.36
Worksheet 31July 12, 2022$12,356.38$74,138.31
Worksheet 100July 12, 2022$3,667.25$22,003.52
Worksheet 22July 12, 2022$2,508.83$15,053.01
Worksheet 19July 12, 2022$1,711.77$10,270.61
Worksheet 106January 6, 2026-$1,250.20$0.00
Worksheet 28July 12, 2022$1,241.76$7,450.56
Worksheet 244July 12, 2022$1,203.93$7,223.63
Worksheet 242July 12, 2022$732.80$4,396.79
Worksheet 43July 12, 2022$599.43$3,596.63

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.