DR-4576 · Mississippi
HURRICANE ZETA
Hurricane · Declared December 31, 2020
Recorded incident start October 28, 2020. Recorded incident end October 29, 2020. Declaration request November 24, 2020.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| George County, Mississippi | IHP · Public Assistance · Hazard Mitigation | March 1, 2021 |
| Greene County, Mississippi | IHP · Public Assistance · Hazard Mitigation | March 1, 2021 |
| Hancock County, Mississippi | IHP · Public Assistance · Hazard Mitigation | March 1, 2021 |
| Harrison County, Mississippi | IHP · Public Assistance · Hazard Mitigation | March 1, 2021 |
| Jackson County, Mississippi | IHP · Public Assistance · Hazard Mitigation | March 1, 2021 |
| Perry County, Mississippi | Public Assistance · Hazard Mitigation | March 1, 2021 |
| Stone County, Mississippi | IHP · Public Assistance · Hazard Mitigation | March 1, 2021 |
| Wayne County, Mississippi | Public Assistance · Hazard Mitigation | March 1, 2021 |
Public Assistance for this declaration
- Project worksheets
- 482
- Federal share obligated
- $123,438,341.60
- Median days to first recorded obligation
- 217
Timing uses 482 dated worksheets and starts on the original declaration date. Earliest first obligation February 18, 2021. Most recent obligation in the project snapshot November 3, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Debris Removal | 49 | $51,264,572.74 |
| Parks, Recreational Facilities, and Other Items | 107 | $34,498,238.76 |
| Utilities | 43 | $18,452,439.19 |
| Buildings and Equipment | 149 | $8,151,855.98 |
| Emergency Protective Measures | 64 | $4,003,369.30 |
| Management Costs | 38 | $3,363,281.29 |
| Water Control Facilities | 1 | $2,120,483.75 |
| Roads and Bridges | 31 | $1,584,100.59 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2021 | 444 |
| 2022 | 24 |
| 2023 | 5 |
| 2024 | 5 |
| 2025 | 3 |
| 2026 | 1 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Harrison County, Mississippi | 241 | $62,389,264.14 |
| George County, Mississippi | 39 | $19,362,107.48 |
| Hancock County, Mississippi | 67 | $17,778,725.48 |
| Jackson County, Mississippi | 70 | $11,498,750.68 |
| Greene County, Mississippi | 3 | $2,319,917.07 |
| Stone County, Mississippi | 2 | $1,468,385.78 |
| Wayne County, Mississippi | 11 | $695,787.76 |
| Perry County, Mississippi | 5 | $111,758.00 |
Projects FEMA labels statewide
- Project worksheets
- 32
- Federal share obligated
- $7,158,562.97
- Median days to first recorded obligation
- 178.5
Timing uses 32 dated worksheets and starts on the original declaration date. Earliest first obligation February 18, 2021. Most recent obligation in the project snapshot February 10, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 6 | $6,019,343.65 |
| Management Costs | 5 | $362,688.41 |
| Buildings and Equipment | 11 | $312,299.28 |
| Emergency Protective Measures | 3 | $301,224.19 |
| Debris Removal | 2 | $100,934.30 |
| Parks, Recreational Facilities, and Other Items | 5 | $62,073.14 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2021 | 32 |
Project worksheet revisions
435 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 454 | July 14, 2026 | -$1,874,806.75 | $438,069.46 |
| Worksheet 497 | October 4, 2024 | $1,658,875.97 | $3,044,268.20 |
| Worksheet 450 | April 26, 2022 | $1,573,731.85 | $9,442,391.08 |
| Worksheet 159 | April 26, 2022 | $1,071,366.37 | $6,428,198.20 |
| Worksheet 65 | March 16, 2023 | $986,199.14 | $2,180,900.54 |
| Worksheet 481 | July 8, 2026 | $863,478.83 | $3,249,911.01 |
| Worksheet 15 | April 8, 2022 | $585,996.31 | $3,515,977.83 |
| Worksheet 444 | April 8, 2022 | $563,588.50 | $3,381,531.01 |
| Worksheet 326 | May 3, 2024 | $540,290.01 | $2,415,980.91 |
| Worksheet 196 | April 8, 2022 | $476,126.24 | $2,856,757.47 |
| Worksheet 423 | May 1, 2026 | -$421,887.34 | $143,374.81 |
| Worksheet 204 | April 8, 2022 | $385,696.22 | $2,314,177.32 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.