DR-4616 · Nebraska
SEVERE STORMS AND STRAIGHT-LINE WINDS
Severe Storm · Declared September 6, 2021
Recorded incident start July 9, 2021. Recorded incident end July 10, 2021. Declaration request August 18, 2021.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Box Butte County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Cass County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Clay County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Douglas County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Fillmore County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Grant County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Hall County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Hamilton County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Madison County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Sarpy County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Saunders County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Sheridan County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| Washington County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
| York County, Nebraska | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 66
- Federal share obligated
- $28,031,370.02
- Median days to first recorded obligation
- 159.5
Timing uses 66 dated worksheets and starts on the original declaration date. Earliest first obligation November 22, 2021. Most recent obligation in the project snapshot October 15, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 23 | $22,286,841.88 |
| Debris Removal | 16 | $4,619,318.77 |
| Parks, Recreational Facilities, and Other Items | 5 | $500,865.19 |
| Management Costs | 16 | $455,725.13 |
| Buildings and Equipment | 2 | $137,772.60 |
| Emergency Protective Measures | 3 | $19,317.58 |
| Roads and Bridges | 1 | $11,528.87 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2021 | 7 |
| 2022 | 57 |
| 2023 | 1 |
| 2024 | 1 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Douglas County, Nebraska | 18 | $18,692,231.63 |
| York County, Nebraska | 6 | $7,794,062.59 |
| Hall County, Nebraska | 8 | $475,764.03 |
| Box Butte County, Nebraska | 5 | $164,390.00 |
| Cass County, Nebraska | 4 | $134,430.16 |
| Madison County, Nebraska | 4 | $119,499.98 |
| Sarpy County, Nebraska | 5 | $116,217.42 |
| Hamilton County, Nebraska | 5 | $55,173.85 |
| Clay County, Nebraska | 2 | $12,041.50 |
Projects FEMA labels statewide
- Project worksheets
- 4
- Federal share obligated
- $351,975.45
- Median days to first recorded obligation
- 256
Timing uses 4 dated worksheets and starts on the original declaration date. Earliest first obligation November 22, 2021. Most recent obligation in the project snapshot May 27, 2022.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Management Costs | 1 | $198,158.00 |
| Utilities | 3 | $153,817.45 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2021 | 1 |
| 2022 | 3 |
Project worksheet revisions
52 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 62 | May 11, 2026 | -$632,988.04 | $185,428.14 |
| Worksheet 57 | September 3, 2026 | $288,590.53 | $595,718.77 |
| Worksheet 44 | October 15, 2026 | -$271,629.91 | $32,418.29 |
| Worksheet 63 | August 27, 2026 | $260,912.78 | $456,173.91 |
| Worksheet 41 | October 25, 2022 | $245,599.41 | $13,029,198.65 |
| Worksheet 31 | April 8, 2022 | $241,392.15 | $1,448,352.91 |
| Worksheet 68 | September 30, 2026 | -$115,174.91 | $43,538.77 |
| Worksheet 56 | January 2, 2025 | -$107,566.18 | $117,177.82 |
| Worksheet 65 | August 25, 2026 | $58,235.38 | $1,592,354.86 |
| Worksheet 40 | April 8, 2022 | $26,660.37 | $159,962.22 |
| Worksheet 12 | April 8, 2022 | $21,432.44 | $128,594.66 |
| Worksheet 46 | October 13, 2026 | -$15,090.55 | $1,801.02 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity