DR-4617 · North Carolina
Project worksheets 2–219
REMNANTS OF TROPICAL STORM FRED
Showing 1–75 of 75 worksheets with dated revisions, in worksheet number order.
Worksheet timelines
| Worksheet | Applicant location | Work category | Last activity date | Last signed change | Federal share in project snapshot |
|---|---|---|---|---|---|
| 2 | Yancey County, North Carolina | Emergency Protective Measures | April 4, 2022 | $2,493.75 | $14,962.50 |
| 3 | Haywood County, North Carolina | Emergency Protective Measures | January 24, 2026 | $674,567.41 | $934,784.69 |
| 5 | Haywood County, North Carolina | Emergency Protective Measures | April 4, 2022 | $578.02 | $3,468.14 |
| 6 | Haywood County, North Carolina | Emergency Protective Measures | April 4, 2022 | $916.43 | $5,498.56 |
| 7 | Haywood County, North Carolina | Utilities | April 4, 2022 | $7,363.73 | $44,182.38 |
| 8 | Yancey County, North Carolina | Utilities | April 4, 2022 | $989.18 | $5,935.12 |
| 9 | Watauga County, North Carolina | Emergency Protective Measures | April 4, 2022 | $1,186.16 | $7,116.96 |
| 10 | Watauga County, North Carolina | Debris Removal | April 4, 2022 | $574.55 | $3,447.31 |
| 11 | Haywood County, North Carolina | Utilities | April 4, 2022 | $4,812.00 | $28,872.00 |
| 12 | Statewide | Emergency Protective Measures | April 4, 2022 | $3,306.53 | $19,839.18 |
| 13 | Haywood County, North Carolina | Emergency Protective Measures | April 4, 2022 | $1,026.50 | $6,159.01 |
| 14 | Unavailable | Utilities | April 4, 2022 | $17,882.96 | $107,297.74 |
| 15 | Madison County, North Carolina | Utilities | April 4, 2022 | $14,075.28 | $84,451.67 |
| 16 | Statewide | Parks, Recreational Facilities, and Other Items | April 4, 2022 | $820.14 | $4,920.80 |
| 17 | Statewide | Parks, Recreational Facilities, and Other Items | April 4, 2022 | $12,329.10 | $73,974.59 |
| 18 | Haywood County, North Carolina | Roads and Bridges | April 4, 2022 | $3,829.54 | $22,977.26 |
| 19 | Haywood County, North Carolina | Roads and Bridges | April 4, 2022 | $9,064.59 | $54,387.53 |
| 20 | Haywood County, North Carolina | Parks, Recreational Facilities, and Other Items | July 1, 2024 | -$16,235.98 | $0.00 |
| 21 | Statewide | Buildings and Equipment | April 4, 2022 | $1,866.00 | $11,196.02 |
| 22 | Haywood County, North Carolina | Emergency Protective Measures | April 4, 2022 | $796.76 | $4,780.58 |
| 25 | Unavailable | Utilities | April 4, 2022 | $1,623.09 | $9,738.52 |
| 27 | Watauga County, North Carolina | Roads and Bridges | April 4, 2022 | $11,415.00 | $68,490.00 |
| 28 | Haywood County, North Carolina | Management Costs | June 4, 2024 | -$265.59 | $0.00 |
| 31 | Haywood County, North Carolina | Roads and Bridges | April 4, 2022 | $2,704.40 | $16,226.38 |
| 32 | Madison County, North Carolina | Management Costs | November 27, 2023 | -$1,718.92 | $2,972.84 |
| 33 | Buncombe County, North Carolina | Buildings and Equipment | April 4, 2022 | $2,702.39 | $16,214.38 |
| 34 | Buncombe County, North Carolina | Utilities | April 4, 2022 | $1,670.46 | $10,022.81 |
| 35 | Haywood County, North Carolina | Emergency Protective Measures | April 4, 2022 | $11,336.99 | $68,021.92 |
| 36 | Haywood County, North Carolina | Utilities | April 4, 2022 | $73,280.15 | $439,680.94 |
| 37 | Haywood County, North Carolina | Emergency Protective Measures | April 4, 2022 | $7,327.05 | $43,962.30 |
| 38 | Buncombe County, North Carolina | Debris Removal | April 4, 2022 | $51,762.95 | $310,577.70 |
| 39 | Buncombe County, North Carolina | Utilities | April 26, 2026 | -$3,375.30 | $0.00 |
| 40 | Buncombe County, North Carolina | Utilities | April 4, 2022 | $8,109.75 | $48,658.52 |
| 41 | Buncombe County, North Carolina | Emergency Protective Measures | April 4, 2022 | $2,836.26 | $17,017.55 |
| 42 | Buncombe County, North Carolina | Parks, Recreational Facilities, and Other Items | April 4, 2022 | $1,154.21 | $6,925.27 |
| 43 | Haywood County, North Carolina | Roads and Bridges | April 4, 2022 | $2,481.52 | $14,889.15 |
| 44 | Haywood County, North Carolina | Management Costs | January 2, 2024 | -$16,896.65 | $7,530.07 |
| 45 | Transylvania County, North Carolina | Roads and Bridges | April 4, 2022 | $6,022.37 | $36,134.25 |
| 47 | Statewide | Debris Removal | April 4, 2022 | $11,755.53 | $70,533.18 |
| 48 | Statewide | Emergency Protective Measures | April 4, 2022 | $4,568.50 | $27,411.03 |
| 50 | Haywood County, North Carolina | Debris Removal | January 8, 2024 | $0.18 | $126,699.85 |
| 51 | Haywood County, North Carolina | Buildings and Equipment | April 4, 2022 | $1,294.12 | $7,764.72 |
| 52 | Buncombe County, North Carolina | Parks, Recreational Facilities, and Other Items | April 4, 2022 | $5,683.17 | $34,099.07 |
| 53 | Statewide | Emergency Protective Measures | April 4, 2022 | $11,209.60 | $67,257.59 |
| 54 | Buncombe County, North Carolina | Roads and Bridges | April 4, 2022 | $805.18 | $4,831.06 |
| 60 | Transylvania County, North Carolina | Parks, Recreational Facilities, and Other Items | May 1, 2024 | $184,542.90 | $354,283.80 |
| 61 | Statewide | Debris Removal | April 4, 2022 | $76,914.30 | $461,485.79 |
| 64 | Haywood County, North Carolina | Emergency Protective Measures | June 2, 2026 | $60,727.74 | $242,910.98 |
| 73 | Watauga County, North Carolina | Management Costs | May 28, 2024 | -$5,375.06 | $0.00 |
| 76 | Transylvania County, North Carolina | Management Costs | May 29, 2025 | -$0.20 | $9,429.85 |
| 92 | Yancey County, North Carolina | Roads and Bridges | June 10, 2024 | $71,465.69 | $192,248.17 |
| 96 | Yancey County, North Carolina | Roads and Bridges | May 29, 2025 | -$134,036.41 | $10,665.00 |
| 99 | Statewide | Management Costs | October 18, 2023 | -$2,249.63 | $372.45 |
| 100 | Haywood County, North Carolina | Parks, Recreational Facilities, and Other Items | July 1, 2024 | -$0.01 | $32,487.60 |
| 110 | Haywood County, North Carolina | Management Costs | January 2, 2024 | -$2,472.01 | $2,472.02 |
| 111 | Haywood County, North Carolina | Management Costs | June 11, 2024 | -$617.20 | $0.00 |
| 119 | Yancey County, North Carolina | Parks, Recreational Facilities, and Other Items | March 4, 2024 | $13,202.68 | $154,021.50 |
| 120 | Buncombe County, North Carolina | Management Costs | June 29, 2026 | -$11,100.41 | $0.00 |
| 122 | Statewide | Roads and Bridges | March 4, 2024 | $43,199.03 | $244,511.73 |
| 123 | Haywood County, North Carolina | Parks, Recreational Facilities, and Other Items | August 24, 2025 | $210,687.60 | $419,172.24 |
| 130 | Haywood County, North Carolina | Debris Removal | October 18, 2023 | -$115,531.34 | $1,263,524.11 |
| 133 | Haywood County, North Carolina | Debris Removal | January 2, 2024 | -$478,496.97 | $1,076,241.68 |
| 143 | Haywood County, North Carolina | Buildings and Equipment | March 10, 2025 | -$421,242.95 | $33,019.06 |
| 146 | Yancey County, North Carolina | Management Costs | December 10, 2025 | -$15,078.84 | $0.00 |
| 147 | Statewide | Roads and Bridges | March 4, 2024 | $0.96 | $164,195.35 |
| 150 | Statewide | Roads and Bridges | May 1, 2024 | $11,808.72 | $254,893.73 |
| 164 | Haywood County, North Carolina | Management Costs | September 22, 2026 | -$33,001.58 | $182,604.25 |
| 165 | Yancey County, North Carolina | Management Costs | April 2, 2024 | -$18,913.42 | $15,720.59 |
| 166 | Unavailable | Management Costs | June 11, 2024 | -$2,693.40 | $0.00 |
| 171 | Buncombe County, North Carolina | Management Costs | July 15, 2024 | -$26,853.40 | $3,367.79 |
| 172 | Transylvania County, North Carolina | Management Costs | January 2, 2024 | -$6,272.15 | $15,092.24 |
| 205 | Statewide | Roads and Bridges | June 25, 2024 | -$150,353.79 | $1,189,844.72 |
| 209 | Statewide | Roads and Bridges | March 10, 2025 | -$36.73 | $1,380,414.58 |
| 212 | Statewide | Roads and Bridges | March 4, 2024 | $12,865.15 | $1,136,783.33 |
| 219 | Statewide | Management Costs | July 14, 2026 | -$364,285.64 | $573,421.06 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity