DR-4717 · North Dakota

Pembina County, North Dakota

FLOODING · Declared July 5, 2023

Programs listed for this county · Public Assistance · Hazard Mitigation

Official FEMA disaster page · Other declarations for this county

Public Assistance for applicants listed in this county

Project worksheets
17
Federal share obligated
$980,011.92
Median days to first recorded obligation
231

Timing uses 17 dated worksheets and starts on the original declaration date. Earliest first obligation January 4, 2024. Most recent obligation in the project snapshot August 15, 2025.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Water Control Facilities3$666,262.12
Roads and Bridges7$212,935.02
Emergency Protective Measures5$63,644.04
Management Costs2$37,170.74
First obligations by year
Year of first recorded obligation
YearWorksheets
202417

Revisions for worksheets with applicants in this county

2 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 112April 16, 2025$106,839.38$516,340.05
Worksheet 108August 15, 2025$48,511.47$131,584.57

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.