DR-4741 · Missouri
Project worksheets 14–316
SEVERE STORMS, STRAIGHT-LINE WINDS, TORNADOES, AND FLOODING
Showing 1–35 of 35 worksheets with dated revisions, in worksheet number order.
Worksheet timelines
| Worksheet | Applicant location | Work category | Last activity date | Last signed change | Federal share in project snapshot |
|---|---|---|---|---|---|
| 14 | Taney County, Missouri | Utilities | May 1, 2025 | -$19,388.87 | $324,583.84 |
| 15 | Unavailable | Management Costs | November 13, 2024 | -$416.40 | $1,046.83 |
| 17 | Statewide | Management Costs | April 20, 2026 | -$2,343.24 | $0.00 |
| 58 | Statewide | Management Costs | February 3, 2025 | -$6,378.32 | $5,123.29 |
| 60 | Ozark County, Missouri | Roads and Bridges | December 12, 2025 | -$64,368.46 | $715,938.18 |
| 61 | Ozark County, Missouri | Roads and Bridges | December 12, 2025 | -$418,077.38 | $706,574.02 |
| 93 | Christian County, Missouri | Management Costs | May 22, 2025 | -$7,112.06 | $7,456.00 |
| 102 | Unavailable | Management Costs | October 1, 2024 | -$1,805.39 | $0.00 |
| 103 | Barton County, Missouri | Management Costs | April 20, 2026 | -$1,016.49 | $0.00 |
| 104 | Maries County, Missouri | Management Costs | May 28, 2025 | -$2,256.55 | $0.00 |
| 105 | Mississippi County, Missouri | Management Costs | May 19, 2026 | -$2,872.60 | $0.00 |
| 115 | Mississippi County, Missouri | Management Costs | September 15, 2026 | -$3,813.74 | $0.00 |
| 121 | Barry County, Missouri | Management Costs | October 1, 2024 | -$6.78 | $1,696.50 |
| 138 | Ozark County, Missouri | Management Costs | October 14, 2026 | -$266.70 | $0.00 |
| 142 | Ozark County, Missouri | Management Costs | September 1, 2026 | -$75,915.92 | $3,028.38 |
| 179 | Bollinger County, Missouri | Utilities | April 8, 2025 | $3,386.27 | $11,959.37 |
| 238 | Madison County, Missouri | Management Costs | October 6, 2026 | -$11,602.58 | $4,299.28 |
| 265 | Iron County, Missouri | Management Costs | December 5, 2024 | -$2,112.15 | $11,372.17 |
| 274 | Dade County, Missouri | Management Costs | January 23, 2025 | -$1,856.31 | $0.00 |
| 275 | Barry County, Missouri | Management Costs | April 28, 2025 | -$3,287.27 | $0.00 |
| 276 | Christian County, Missouri | Management Costs | November 3, 2025 | -$12,355.16 | $0.00 |
| 280 | Bates County, Missouri | Management Costs | December 3, 2024 | -$3,298.02 | $7,339.98 |
| 282 | Grundy County, Missouri | Management Costs | April 20, 2026 | -$1,593.51 | $678.75 |
| 283 | Statewide | Management Costs | January 21, 2025 | -$7,152.93 | $4,881.70 |
| 289 | Unavailable | Management Costs | February 6, 2025 | -$1,679.79 | $10,392.88 |
| 293 | Vernon County, Missouri | Management Costs | February 10, 2026 | -$1,335.69 | $0.00 |
| 299 | Knox County, Missouri | Management Costs | October 14, 2026 | -$3,679.98 | $11,036.00 |
| 300 | Grundy County, Missouri | Management Costs | May 8, 2025 | -$2,829.92 | $1,297.51 |
| 303 | Barry County, Missouri | Management Costs | November 14, 2025 | -$1,399.10 | $0.00 |
| 304 | Ozark County, Missouri | Management Costs | November 2, 2026 | -$10,713.46 | $0.00 |
| 309 | Barry County, Missouri | Management Costs | September 11, 2025 | -$8,829.50 | $0.00 |
| 311 | Worth County, Missouri | Management Costs | April 8, 2026 | -$933.02 | $21,325.67 |
| 313 | Scott County, Missouri | Management Costs | April 20, 2026 | -$13,333.57 | $579.98 |
| 314 | Barry County, Missouri | Management Costs | January 23, 2026 | -$300.00 | $0.00 |
| 316 | Greene County, Missouri | Management Costs | January 2, 2026 | -$89,094.92 | $28,104.85 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity