DR-4742 · Tennessee
SEVERE STORMS, STRAIGHT-LINE WINDS, AND TORNADO
Severe Storm · Declared September 27, 2023
Recorded incident start August 7, 2023. Recorded incident end August 7, 2023. Declaration request September 5, 2023.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Bledsoe County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Coffee County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Cumberland County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Jefferson County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Knox County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Loudon County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Meigs County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Rhea County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Roane County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
| Van Buren County, Tennessee | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 54
- Federal share obligated
- $10,089,089.39
- Median days to first recorded obligation
- 195
Timing uses 54 dated worksheets and starts on the original declaration date. Earliest first obligation November 29, 2023. Most recent obligation in the project snapshot September 2, 2025.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 12 | $6,559,360.31 |
| Debris Removal | 13 | $2,046,714.97 |
| Management Costs | 14 | $925,114.22 |
| Emergency Protective Measures | 10 | $443,110.40 |
| Roads and Bridges | 3 | $104,371.99 |
| Buildings and Equipment | 2 | $10,417.50 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2023 | 5 |
| 2024 | 47 |
| 2025 | 2 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Knox County, Tennessee | 12 | $4,102,303.79 |
| Loudon County, Tennessee | 7 | $1,460,145.33 |
| Meigs County, Tennessee | 2 | $950,518.44 |
| Rhea County, Tennessee | 5 | $259,914.47 |
| Jefferson County, Tennessee | 6 | $114,339.55 |
| Bledsoe County, Tennessee | 4 | $102,379.43 |
Projects FEMA labels statewide
- Project worksheets
- 12
- Federal share obligated
- $2,394,283.57
- Median days to first recorded obligation
- 228.5
Timing uses 12 dated worksheets and starts on the original declaration date. Earliest first obligation November 29, 2023. Most recent obligation in the project snapshot October 11, 2024.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 4 | $937,524.42 |
| Management Costs | 3 | $870,330.22 |
| Emergency Protective Measures | 2 | $297,942.65 |
| Debris Removal | 2 | $280,986.28 |
| Buildings and Equipment | 1 | $7,500.00 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2023 | 2 |
| 2024 | 10 |
Project worksheet revisions
3 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 29 | January 13, 2025 | -$12,387.53 | $6,004.00 |
| Worksheet 44 | September 2, 2025 | -$7,651.43 | $1,009.31 |
| Worksheet 3 | April 2, 2024 | $6,524.68 | $6,524.68 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.