DR-4766 · Rhode Island

SEVERE STORMS AND FLOODING

Severe Storm · Declared March 20, 2024

Recorded incident start January 9, 2024. Recorded incident end January 13, 2024. Declaration request March 6, 2024.

Open the official FEMA disaster page · Declaration data

County designations and filing dates

County programs listed by FEMA
CountyPrograms listedIndividual Assistance filing date
Kent County, Rhode IslandIHP · Public Assistance · Hazard MitigationMay 20, 2024

Other designated areas

FEMA area records
Area listedPrograms listed
Providence (County)(in PMSA 6060,6480)IHP · Hazard Mitigation
Washington (County)(in (P)MSA 5520,6480)IHP · Public Assistance · Hazard Mitigation
Newport (County)(in PMSA 2480,6480)Public Assistance · Hazard Mitigation

Public Assistance for this declaration

Project worksheets
80
Federal share obligated
$4,899,278.86
Median days to first recorded obligation
315

Timing uses 80 dated worksheets and starts on the original declaration date. Earliest first obligation July 30, 2024. Most recent obligation in the project snapshot August 14, 2026.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Roads and Bridges30$1,826,140.75
Parks, Recreational Facilities, and Other Items14$988,138.86
Utilities1$503,312.76
Management Costs10$476,860.06
Water Control Facilities4$383,638.37
Debris Removal9$358,103.79
Emergency Protective Measures10$302,691.07
Buildings and Equipment2$60,393.20
First obligations by year
Year of first recorded obligation
YearWorksheets
202429
202548
20263

Projects by applicant county

Applicant location recorded by FEMA
Applicant countyWorksheetsFederal share obligated
Kent County, Rhode Island25$2,035,737.71

Projects FEMA labels statewide

Project worksheets
6
Federal share obligated
$562,476.85
Median days to first recorded obligation
235

Timing uses 6 dated worksheets and starts on the original declaration date. Earliest first obligation July 30, 2024. Most recent obligation in the project snapshot September 17, 2025.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Management Costs1$397,361.69
Emergency Protective Measures2$105,689.38
Roads and Bridges2$31,547.36
Debris Removal1$27,878.42
First obligations by year
Year of first recorded obligation
YearWorksheets
20245
20251

Project worksheet revisions

1 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 28September 17, 2025$113,633.83$397,361.69

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.

FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity