DR-4767 · Alaska
SEVERE STORM, FLOODING, AND LANDSLIDES
Mud/Landslide · Declared April 6, 2024
Recorded incident start November 20, 2023. Recorded incident end November 20, 2023. Declaration request January 4, 2024.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Prince of Wales-Hyder Census Area, Alaska | Public Assistance · Hazard Mitigation | Unavailable |
| Wrangell City and Borough, Alaska | Public Assistance · Hazard Mitigation | Unavailable |
Other designated areas
| Area listed | Programs listed |
|---|---|
| Southeast Islands Regional Educational Attendance Ar | Public Assistance · Hazard Mitigation |
Public Assistance for this declaration
- Project worksheets
- 15
- Federal share obligated
- $2,291,318.53
- Median days to first recorded obligation
- 520
Timing uses 15 dated worksheets and starts on the original declaration date. Earliest first obligation October 23, 2024. Most recent obligation in the project snapshot September 24, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Debris Removal | 5 | $947,596.68 |
| Roads and Bridges | 2 | $793,663.13 |
| Emergency Protective Measures | 5 | $355,428.51 |
| Management Costs | 2 | $147,258.84 |
| Utilities | 1 | $47,371.37 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2024 | 2 |
| 2025 | 6 |
| 2026 | 7 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Prince of Wales-Hyder Census Area, Alaska | 6 | $847,888.56 |
Projects FEMA labels statewide
- Project worksheets
- 4
- Federal share obligated
- $598,660.98
- Median days to first recorded obligation
- 605.5
Timing uses 4 dated worksheets and starts on the original declaration date. Earliest first obligation November 22, 2024. Most recent obligation in the project snapshot September 1, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Debris Removal | 2 | $435,134.02 |
| Management Costs | 1 | $94,460.77 |
| Emergency Protective Measures | 1 | $69,066.19 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2024 | 1 |
| 2025 | 1 |
| 2026 | 2 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.