DR-4778 · Nebraska

SEVERE STORMS, STRAIGHT-LINE WINDS, AND TORNADOES

Tornado · Declared May 3, 2024

Recorded incident start April 25, 2024. Recorded incident end April 27, 2024. Declaration request May 1, 2024.

Open the official FEMA disaster page · Declaration data

County designations and filing dates

County programs listed by FEMA
CountyPrograms listedIndividual Assistance filing date
Boone County, NebraskaPublic Assistance · Hazard MitigationJuly 15, 2024
Douglas County, NebraskaIHP · Public Assistance · Hazard MitigationJuly 15, 2024
Greeley County, NebraskaPublic Assistance · Hazard MitigationJuly 15, 2024
Howard County, NebraskaPublic Assistance · Hazard MitigationJuly 15, 2024
Sherman County, NebraskaPublic Assistance · Hazard MitigationJuly 15, 2024
Washington County, NebraskaIHP · Public Assistance · Hazard MitigationJuly 15, 2024

Public Assistance for this declaration

Project worksheets
44
Federal share obligated
$8,825,137.58
Median days to first recorded obligation
419.5

Timing uses 44 dated worksheets and starts on the original declaration date. Earliest first obligation October 3, 2024. Most recent obligation in the project snapshot November 4, 2026.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Utilities6$5,938,757.24
Debris Removal8$882,268.15
Management Costs13$725,196.52
Emergency Protective Measures7$579,985.78
Buildings and Equipment4$521,950.52
Parks, Recreational Facilities, and Other Items2$107,465.51
Roads and Bridges4$69,513.86
First obligations by year
Year of first recorded obligation
YearWorksheets
20249
202529
20266

Projects by applicant county

Applicant location recorded by FEMA
Applicant countyWorksheetsFederal share obligated
Douglas County, Nebraska29$6,220,437.20
Howard County, Nebraska2$703,637.63
Washington County, Nebraska3$142,543.20

Projects FEMA labels statewide

Project worksheets
2
Federal share obligated
$541,235.61
Median days to first recorded obligation
531

Timing uses 2 dated worksheets and starts on the original declaration date. Earliest first obligation January 15, 2025. Most recent obligation in the project snapshot July 17, 2026.

Funded worksheets by category
Work categoryWorksheetsFederal share obligated
Emergency Protective Measures1$288,593.89
Management Costs1$252,641.72
First obligations by year
Year of first recorded obligation
YearWorksheets
20251
20261

Project worksheet revisions

6 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.

Browse every worksheet timeline for this declaration

Latest documented revisions
WorksheetLast date in activity fileLast signed changeNet in activity file
Worksheet 35November 21, 2025-$71,617.50$7,076.37
Worksheet 16January 6, 2026$4,060.67$22,693.16
Worksheet 14November 4, 2026$2,396.86$3,188,549.56
Worksheet 42February 17, 2025-$477.65$2,657.55
Worksheet 45June 26, 2025-$85.14$2,000.86
Worksheet 18September 25, 2026-$19.30$941,992.20

How to read these FEMA records

America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.

FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity