DR-4787 · West Virginia
SEVERE STORMS, FLOODING, LANDSLIDES, AND MUDSLIDES
Flood · Declared May 24, 2024
Recorded incident start April 11, 2024. Recorded incident end April 12, 2024. Declaration request May 9, 2024.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Boone County, West Virginia | IHP · Public Assistance · Hazard Mitigation | November 2, 2024 |
| Brooke County, West Virginia | Public Assistance · Hazard Mitigation | November 2, 2024 |
| Doddridge County, West Virginia | Public Assistance · Hazard Mitigation | November 2, 2024 |
| Gilmer County, West Virginia | Public Assistance · Hazard Mitigation | November 2, 2024 |
| Hancock County, West Virginia | IHP · Public Assistance · Hazard Mitigation | November 2, 2024 |
| Kanawha County, West Virginia | IHP · Hazard Mitigation | November 2, 2024 |
| Lincoln County, West Virginia | Public Assistance · Hazard Mitigation | November 2, 2024 |
| Marshall County, West Virginia | IHP · Public Assistance · Hazard Mitigation | November 2, 2024 |
| Ohio County, West Virginia | IHP · Public Assistance · Hazard Mitigation | November 2, 2024 |
| Roane County, West Virginia | IHP · Hazard Mitigation | November 2, 2024 |
| Tyler County, West Virginia | Public Assistance · Hazard Mitigation | November 2, 2024 |
| Wetzel County, West Virginia | IHP · Public Assistance · Hazard Mitigation | November 2, 2024 |
| Wood County, West Virginia | IHP · Hazard Mitigation | November 2, 2024 |
Public Assistance for this declaration
- Project worksheets
- 65
- Federal share obligated
- $15,073,002.67
- Median days to first recorded obligation
- 259
Timing uses 65 dated worksheets and starts on the original declaration date. Earliest first obligation July 2, 2024. Most recent obligation in the project snapshot July 10, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 45 | $8,841,731.72 |
| Utilities | 2 | $5,489,583.74 |
| Management Costs | 7 | $634,076.66 |
| Debris Removal | 4 | $33,433.09 |
| Water Control Facilities | 1 | $31,125.00 |
| Parks, Recreational Facilities, and Other Items | 3 | $21,823.38 |
| Emergency Protective Measures | 3 | $21,229.08 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2024 | 7 |
| 2025 | 57 |
| 2026 | 1 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Marshall County, West Virginia | 37 | $6,824,840.12 |
| Ohio County, West Virginia | 4 | $5,851,481.97 |
| Kanawha County, West Virginia | 1 | $196,291.65 |
| Hancock County, West Virginia | 5 | $40,413.64 |
| Boone County, West Virginia | 1 | $9,213.10 |
| Wetzel County, West Virginia | 1 | $3,130.29 |
| Doddridge County, West Virginia | 1 | $0.00 |
Projects FEMA labels statewide
- Project worksheets
- 1
- Federal share obligated
- $231,030.63
- Median days to first recorded obligation
- 39
Timing uses 1 dated worksheets and starts on the original declaration date. Earliest first obligation July 2, 2024. Most recent obligation in the project snapshot July 2, 2024.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Management Costs | 1 | $231,030.63 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2024 | 1 |
Project worksheet revisions
4 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 71 | July 10, 2026 | -$9,924.61 | $0.00 |
| Worksheet 73 | January 12, 2026 | -$5,807.28 | $15,473.34 |
| Worksheet 100 | October 2, 2025 | -$2,528.88 | $0.00 |
| Worksheet 99 | June 5, 2026 | -$326.01 | $2,511.88 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity