DR-4788 · Arkansas
SEVERE STORMS, STRAIGHT-LINE WINDS, TORNADOES, AND FLOODING
Severe Storm · Declared May 30, 2024
Recorded incident start May 24, 2024. Recorded incident end May 27, 2024. Declaration request May 29, 2024.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Baxter County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 28, 2024 |
| Benton County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 28, 2024 |
| Boone County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 28, 2024 |
| Carroll County, Arkansas | Public Assistance · Hazard Mitigation | August 28, 2024 |
| Fulton County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 28, 2024 |
| Greene County, Arkansas | IHP · Hazard Mitigation | August 28, 2024 |
| Madison County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 28, 2024 |
| Marion County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 28, 2024 |
| Nevada County, Arkansas | Public Assistance · Hazard Mitigation | August 28, 2024 |
| Randolph County, Arkansas | IHP · Public Assistance · Hazard Mitigation | August 28, 2024 |
| Sharp County, Arkansas | Public Assistance · Hazard Mitigation | August 28, 2024 |
Public Assistance for this declaration
- Project worksheets
- 231
- Federal share obligated
- $79,587,459.10
- Median days to first recorded obligation
- 308
Timing uses 231 dated worksheets and starts on the original declaration date. Earliest first obligation June 27, 2024. Most recent obligation in the project snapshot November 4, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Debris Removal | 36 | $37,153,184.35 |
| Utilities | 16 | $29,354,058.08 |
| Management Costs | 29 | $3,870,465.74 |
| Parks, Recreational Facilities, and Other Items | 33 | $2,942,842.35 |
| Buildings and Equipment | 51 | $2,778,757.65 |
| Emergency Protective Measures | 46 | $2,183,223.09 |
| Roads and Bridges | 20 | $1,304,927.84 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2024 | 63 |
| 2025 | 157 |
| 2026 | 11 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Benton County, Arkansas | 123 | $39,427,085.13 |
| Baxter County, Arkansas | 23 | $4,382,926.87 |
| Marion County, Arkansas | 12 | $1,070,582.62 |
| Nevada County, Arkansas | 9 | $924,506.03 |
| Boone County, Arkansas | 6 | $367,481.57 |
| Randolph County, Arkansas | 9 | $268,071.22 |
| Madison County, Arkansas | 3 | $186,191.40 |
| Carroll County, Arkansas | 9 | $176,007.74 |
| Sharp County, Arkansas | 4 | $96,903.94 |
| Fulton County, Arkansas | 4 | $92,692.37 |
Projects FEMA labels statewide
- Project worksheets
- 29
- Federal share obligated
- $32,595,010.21
- Median days to first recorded obligation
- 308
Timing uses 29 dated worksheets and starts on the original declaration date. Earliest first obligation June 27, 2024. Most recent obligation in the project snapshot November 4, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 4 | $27,086,842.24 |
| Debris Removal | 3 | $2,507,536.32 |
| Management Costs | 7 | $2,090,192.73 |
| Emergency Protective Measures | 4 | $344,338.15 |
| Parks, Recreational Facilities, and Other Items | 3 | $294,121.45 |
| Buildings and Equipment | 8 | $271,979.32 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2024 | 12 |
| 2025 | 13 |
| 2026 | 4 |
Project worksheet revisions
14 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 5 | August 6, 2026 | -$568,929.78 | $2,042,976.27 |
| Worksheet 402 | June 30, 2026 | -$326,532.87 | $306,372.52 |
| Worksheet 49 | April 8, 2025 | $243,325.78 | $548,637.84 |
| Worksheet 257 | May 14, 2026 | $17,021.61 | $1,733,888.91 |
| Worksheet 216 | May 14, 2026 | $14,188.74 | $12,201,989.46 |
| Worksheet 197 | December 12, 2025 | $5,090.25 | $24,275.19 |
| Worksheet 206 | June 1, 2026 | -$3,804.00 | $2,653,999.71 |
| Worksheet 131 | April 7, 2025 | $3,763.71 | $9,388.71 |
| Worksheet 190 | June 6, 2025 | $3,716.81 | $16,353.16 |
| Worksheet 394 | September 17, 2026 | -$3,684.48 | $57,123.93 |
| Worksheet 364 | September 18, 2026 | -$1,409.11 | $43,252.12 |
| Worksheet 356 | October 7, 2026 | -$98.68 | $4,168.32 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity