DR-4862 · Oklahoma
SEVERE STORMS, STRAIGHT-LINE WINDS, TORNADOES, AND FLOODING
Severe Storm · Declared March 18, 2025
Recorded incident start November 2, 2024. Recorded incident end November 5, 2024. Declaration request December 20, 2024.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Adair County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Garvin County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Jefferson County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Lincoln County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Okfuskee County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Oklahoma County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Stephens County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
| Washita County, Oklahoma | Public Assistance · Hazard Mitigation | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 49
- Federal share obligated
- $4,976,005.36
- Median days to first recorded obligation
- 146
Timing uses 49 dated worksheets and starts on the original declaration date. Earliest first obligation June 10, 2025. Most recent obligation in the project snapshot July 10, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 11 | $1,445,196.62 |
| Debris Removal | 7 | $948,876.68 |
| Buildings and Equipment | 1 | $848,284.50 |
| Emergency Protective Measures | 7 | $765,211.77 |
| Management Costs | 16 | $697,697.56 |
| Roads and Bridges | 6 | $266,238.23 |
| Parks, Recreational Facilities, and Other Items | 1 | $4,500.00 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2025 | 46 |
| 2026 | 3 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Oklahoma County, Oklahoma | 13 | $1,042,889.28 |
| Okfuskee County, Oklahoma | 7 | $244,753.52 |
| Stephens County, Oklahoma | 7 | $211,807.55 |
| Lincoln County, Oklahoma | 2 | $44,433.31 |
Projects FEMA labels statewide
- Project worksheets
- 20
- Federal share obligated
- $3,432,121.70
- Median days to first recorded obligation
- 146
Timing uses 20 dated worksheets and starts on the original declaration date. Earliest first obligation June 10, 2025. Most recent obligation in the project snapshot July 10, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Utilities | 9 | $1,323,477.56 |
| Buildings and Equipment | 1 | $848,284.50 |
| Management Costs | 8 | $642,045.60 |
| Emergency Protective Measures | 2 | $618,314.04 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2025 | 17 |
| 2026 | 3 |
Project worksheet revisions
9 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 54 | June 26, 2026 | -$21,659.55 | $0.00 |
| Worksheet 50 | January 6, 2026 | -$20,355.17 | $3,256.52 |
| Worksheet 46 | May 5, 2026 | -$9,803.56 | $21,227.47 |
| Worksheet 49 | September 26, 2025 | -$7,364.04 | $3,782.20 |
| Worksheet 52 | April 21, 2026 | -$6,931.66 | $3,690.88 |
| Worksheet 51 | January 6, 2026 | -$5,503.82 | $3,992.18 |
| Worksheet 53 | January 6, 2026 | -$2,222.52 | $5,046.26 |
| Worksheet 45 | April 21, 2026 | -$1,847.04 | $4,404.37 |
| Worksheet 47 | January 6, 2026 | -$577.85 | $6,560.25 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.