DR-4885 · Missouri
SEVERE STORMS AND FLOODING
Severe Storm · Declared July 22, 2025
Recorded incident start May 23, 2025. Recorded incident end May 26, 2025. Declaration request June 21, 2025.
County designations and filing dates
| County | Programs listed | Individual Assistance filing date |
|---|---|---|
| Dade County, Missouri | Public Assistance | Unavailable |
| Douglas County, Missouri | Public Assistance | Unavailable |
| Ozark County, Missouri | Public Assistance | Unavailable |
| Vernon County, Missouri | Public Assistance | Unavailable |
| Webster County, Missouri | Public Assistance | Unavailable |
Public Assistance for this declaration
- Project worksheets
- 71
- Federal share obligated
- $13,053,830.98
- Median days to first recorded obligation
- 303
Timing uses 71 dated worksheets and starts on the original declaration date. Earliest first obligation September 25, 2025. Most recent obligation in the project snapshot October 21, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 44 | $11,290,437.97 |
| Management Costs | 20 | $1,534,544.79 |
| Debris Removal | 7 | $228,848.22 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2025 | 6 |
| 2026 | 65 |
Projects by applicant county
| Applicant county | Worksheets | Federal share obligated |
|---|---|---|
| Vernon County, Missouri | 36 | $4,589,393.06 |
| Ozark County, Missouri | 7 | $2,426,538.93 |
| Douglas County, Missouri | 12 | $2,240,089.19 |
| Webster County, Missouri | 7 | $710,230.89 |
| Dade County, Missouri | 6 | $125,182.09 |
Projects FEMA labels statewide
- Project worksheets
- 3
- Federal share obligated
- $2,962,396.82
- Median days to first recorded obligation
- 401
Timing uses 3 dated worksheets and starts on the original declaration date. Earliest first obligation September 25, 2025. Most recent obligation in the project snapshot October 21, 2026.
| Work category | Worksheets | Federal share obligated |
|---|---|---|
| Roads and Bridges | 1 | $2,013,845.47 |
| Management Costs | 2 | $948,551.35 |
First obligations by year
| Year | Worksheets |
|---|---|
| 2025 | 1 |
| 2026 | 2 |
Project worksheet revisions
2 worksheets have dated revisions. The table shows up to 12 of the largest last revisions by dollar amount.
Browse every worksheet timeline for this declaration
| Worksheet | Last date in activity file | Last signed change | Net in activity file |
|---|---|---|---|
| Worksheet 57 | April 20, 2026 | -$19,396.38 | $4,340.58 |
| Worksheet 56 | April 20, 2026 | -$4,760.32 | $919.20 |
How to read these FEMA records
- Declaration and program designations follow the OpenFEMA extract dated November 6, 2026. County matches require the declared county code and a matching place name. The original declaration date anchors elapsed-time calculations. Local program designations may have changed after that date.
- Household figures combine available owner or renter registration buckets within a declaration and county. The approved amounts come from FEMA’s Individuals and Households Program data. A figure covers published buckets with consistent registration counts and amounts.
- The project snapshot was refreshed by FEMA on November 10, 2026. Its federal share is the amount FEMA obligated to a public-assistance recipient for approved work. Applicant geography describes the organization’s location or statewide classification. First and last obligation dates describe grant records.
- Project timelines use matching worksheet and applicant IDs. Each version’s signed amount comes from FEMA grant award activity, which contains entries through November 10, 2026. Negative entries reduce the recorded obligation. A worksheet may have later accounting activity after the project snapshot.
America.co analysis of Federal Emergency Management Agency OpenFEMA data, retrieved November 10, 2026.
FEMA declarations · Owner assistance data · Renter assistance data · Funded project data · Grant award activity