America.co

AZ0403175 · Arizona

LOCKETT ESTATES

Federal fiscal 2026Q3 · EPA violation and follow-up records

Violation records shown
22
EPA health-based flag
2
Health-based records unresolved in this snapshot
0
Monitoring and reporting records
10

Counties listed by EPA · Coconino County, Arizona

Open the EPA system record

Find the utility’s annual water quality report. For current advisories, check the utility or local drinking-water authority.

Violations and what followed

Among 18 resolved records with both dates, the median interval from recorded noncompliance start to EPA’s return-to-compliance date was 305.5 days. The interval uses the reporting periods and dates on file.

  1. Other or unclassified · Unaddressed by formal action

    Consumer Confidence Report Inadequate ReportingViolation 21 · Consumer Confidence Rule · Consumer Confidence Rule

    Noncompliance period start October 2, 2025 · first reported February 24, 2026

    1 linked action
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    62October 16, 2025InformalState Violation/Reminder Notice
  2. Other or unclassified · Resolved

    Public Notification Violation for NPDWR ViolationViolation 20 · Public Notice · Public Notice Rule and Revised PN Rule

    Noncompliance period start August 14, 2025 · period end October 2, 2025 · first reported February 24, 2026 · EPA return-to-compliance field October 2, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    58September 23, 2025InformalState Violation/Reminder Notice
    73October 2, 2025ResolvingState Compliance achieved
  3. Monitoring or reporting · Resolved

    Lead Consumer NoticeViolation 25 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start August 7, 2025 · period end March 23, 2026 · first reported May 14, 2026 · EPA return-to-compliance field March 23, 2026

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    78March 23, 2026InformalState Violation/Reminder Notice
    79March 23, 2026ResolvingState Compliance achieved
  4. Other or unclassified · Unaddressed by formal action

    Consumer Confidence Report Complete Failure to ReportViolation 22 · Consumer Confidence Rule · Consumer Confidence Rule

    Noncompliance period start July 1, 2025 · first reported February 24, 2026

    1 linked action
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    64October 16, 2025InformalState Violation/Reminder Notice
  5. Monitoring or reporting · Resolved

    Initial Tap Sampling for Pb and CuViolation 19 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start January 1, 2025 · period end July 7, 2025 · first reported February 24, 2026 · EPA return-to-compliance field July 7, 2025

    4 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    53February 21, 2025InformalState Violation/Reminder Notice
    54February 21, 2025InformalState Public Notification requested
    66July 7, 2025ResolvingState Compliance achieved
    75January 27, 2026InformalState Public Notification received
  6. Other or unclassified · Resolved

    Public Notification Violation for NPDWR ViolationViolation 18 · Public Notice · Public Notice Rule and Revised PN Rule

    Noncompliance period start December 20, 2024 · period end October 2, 2025 · first reported February 24, 2026 · EPA return-to-compliance field October 2, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    51January 27, 2025InformalState Violation/Reminder Notice
    67October 2, 2025ResolvingState Compliance achieved
  7. EPA health-based flag · Resolved

    LSL InventoryViolation 17 · LEAD AND COPPER RULE REVISIONS · Lead and Copper Rule Revisions

    Noncompliance period start October 17, 2024 · period end November 21, 2024 · first reported February 24, 2026 · EPA return-to-compliance field November 21, 2024

    4 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    45November 19, 2024InformalState Violation/Reminder Notice
    46November 19, 2024InformalState Public Notification requested
    48November 21, 2024ResolvingState Compliance achieved
    68January 27, 2026InformalState Public Notification received
  8. Monitoring or reporting · Resolved

    LSL ReportingViolation 15 · LEAD AND COPPER RULE REVISIONS · Lead and Copper Rule Revisions

    Noncompliance period start October 17, 2024 · period end November 4, 2024 · first reported February 24, 2026 · EPA return-to-compliance field November 4, 2024

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    39November 4, 2024ResolvingState Compliance achieved
    37November 7, 2024InformalState Violation/Reminder Notice
  9. Other or unclassified · Resolved

    Consumer Confidence Report Inadequate ReportingViolation 14 · Consumer Confidence Rule · Consumer Confidence Rule

    Noncompliance period start October 2, 2024 · period end June 27, 2024 · first reported February 24, 2026 · EPA return-to-compliance field June 27, 2024

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    40June 27, 2024ResolvingState Compliance achieved
    35October 21, 2024InformalState Violation/Reminder Notice
  10. Other or unclassified · Resolved

    Public Notification Violation for NPDWR ViolationViolation 13 · Public Notice · Public Notice Rule and Revised PN Rule

    Noncompliance period start July 2, 2024 · period end October 2, 2025 · first reported February 24, 2026 · EPA return-to-compliance field October 2, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    33August 16, 2024InformalState Violation/Reminder Notice
    71October 2, 2025ResolvingState Compliance achieved
  11. Monitoring or reporting · Resolved

    Lead Consumer NoticeViolation 16 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start April 2, 2024 · period end October 4, 2025 · first reported February 24, 2026 · EPA return-to-compliance field October 4, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    43November 18, 2024InformalState Violation/Reminder Notice
    61October 4, 2025ResolvingState Compliance achieved
  12. Other or unclassified · Resolved

    Public Notification Violation for NPDWR ViolationViolation 11 · Public Notice · Public Notice Rule and Revised PN Rule

    Noncompliance period start January 2, 2024 · period end October 2, 2025 · first reported February 24, 2026 · EPA return-to-compliance field October 2, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    28February 16, 2024InformalState Violation/Reminder Notice
    69October 2, 2025ResolvingState Compliance achieved
  13. Monitoring or reporting · Resolved

    Initial Tap Sampling for Pb and CuViolation 12 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start January 1, 2024 · period end July 7, 2025 · first reported February 24, 2026 · EPA return-to-compliance field July 7, 2025

    4 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    30August 13, 2024InformalState Violation/Reminder Notice
    31August 13, 2024InformalState Public Notification requested
    66July 7, 2025ResolvingState Compliance achieved
    74January 27, 2026InformalState Public Notification received
  14. Other or unclassified · Resolved

    Consumer Confidence Report Inadequate ReportingViolation 9 · Consumer Confidence Rule · Consumer Confidence Rule

    Noncompliance period start October 2, 2023 · period end November 15, 2024 · first reported February 24, 2026 · EPA return-to-compliance field November 15, 2024

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    23October 20, 2023InformalState Violation/Reminder Notice
    41November 15, 2024ResolvingState Compliance achieved
  15. Other or unclassified · Resolved

    Consumer Confidence Report Complete Failure to ReportViolation 8 · Consumer Confidence Rule · Consumer Confidence Rule

    Noncompliance period start July 1, 2023 · period end November 15, 2024 · first reported February 24, 2026 · EPA return-to-compliance field November 15, 2024

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    21October 20, 2023InformalState Violation/Reminder Notice
    42November 15, 2024ResolvingState Compliance achieved
  16. Monitoring or reporting · Resolved

    Initial Tap Sampling for Pb and CuViolation 7 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start July 1, 2023 · period end November 22, 2023 · first reported February 24, 2026 · EPA return-to-compliance field November 22, 2023

    4 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    18August 17, 2023InformalState Violation/Reminder Notice
    19August 17, 2023InformalState Public Notification requested
    49November 22, 2023ResolvingState Compliance achieved
    72January 27, 2026InformalState Public Notification received
  17. Other or unclassified · Resolved

    Public Notification Violation for NPDWR ViolationViolation 6 · Public Notice · Public Notice Rule and Revised PN Rule

    Noncompliance period start May 31, 2023 · period end October 2, 2025 · first reported February 24, 2026 · EPA return-to-compliance field October 2, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    16June 20, 2023InformalState Violation/Reminder Notice
    76October 2, 2025ResolvingState Compliance achieved
  18. Monitoring or reporting · Resolved

    Initial Tap Sampling for Pb and CuViolation 4 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start January 1, 2023 · period end November 22, 2023 · first reported February 24, 2026 · EPA return-to-compliance field November 22, 2023

    4 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    11February 17, 2023InformalState Violation/Reminder Notice
    12February 17, 2023InformalState Public Notification requested
    49November 22, 2023ResolvingState Compliance achieved
    70January 27, 2026InformalState Public Notification received
  19. EPA health-based flag · Resolved

    Failure To Address DeficiencyViolation 10 · Groundwater Rule · Ground Water Rule

    Noncompliance period start October 5, 2022 · period end May 31, 2023 · first reported March 29, 2024 · EPA return-to-compliance field May 31, 2023

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    50May 31, 2023ResolvingState Compliance achieved
    25December 29, 2023InformalState Violation/Reminder Notice
  20. Monitoring or reporting · Resolved

    Lead Consumer NoticeViolation 3 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start October 1, 2022 · period end July 7, 2022 · first reported February 15, 2023 · EPA return-to-compliance field July 7, 2022

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    60July 7, 2022ResolvingState Compliance achieved
    8December 2, 2022InformalState Violation/Reminder Notice
  21. Monitoring or reporting · Resolved

    Initial Tap Sampling for Pb and CuViolation 2 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start July 1, 2022 · period end November 22, 2023 · first reported November 16, 2022 · EPA return-to-compliance field November 22, 2023

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    7July 20, 2022ResolvingState Compliance achieved
    57November 22, 2023ResolvingState Compliance achieved
  22. Monitoring or reporting · Resolved

    Monitoring, Routine (RTCR)Violation 1 · Revised Total Coliform Rule · Revised Total Coliform Rule

    Noncompliance period start April 1, 2022 · period end April 30, 2022 · first reported August 15, 2022 · EPA return-to-compliance field April 30, 2022

    4 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    1May 30, 2022InformalState Violation/Reminder Notice
    2May 30, 2022InformalState Public Notification requested
    4June 1, 2022ResolvingState Compliance achieved
    77January 27, 2026InformalState Public Notification received

EPA data and scope

How to read the records

The enforcement snapshot is federal fiscal 2026Q3. The EPA archive labels its violation file October 13, 2026. EPA says federal reporting can lag by several months. For current advisories, check your utility or local drinking-water authority.

EPA data dictionary and files · EPA reporting and enforcement FAQ · Find an annual water quality report · How to get the report from your utility