America.co

NJ1427018 · New Jersey

MORRIS CHASE/MORRIS HUNT PCWS

Federal fiscal 2026Q3 · EPA violation and follow-up records

Violation records shown
19
EPA health-based flag
1
Health-based records unresolved in this snapshot
0
Monitoring and reporting records
14

Counties listed by EPA · Morris County, New Jersey

Open the EPA system record

Find the utility’s annual water quality report. For current advisories, check the utility or local drinking-water authority.

Violations and what followed

Among 10 resolved records with both dates, the median interval from recorded noncompliance start to EPA’s return-to-compliance date was 300.5 days. The interval uses the reporting periods and dates on file.

  1. Monitoring or reporting · Unaddressed by formal action

    Follow-up Or Routine LCR Tap M/RViolation 180 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start January 1, 2026 · first reported June 30, 2026

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    138June 15, 2026InformalState Formal Notice of Violation issued
    139June 15, 2026InformalState Public Notification requested
  2. Monitoring or reporting · Archived

    Monitoring, RegularViolation 179 · ETHYLENE DIBROMIDE · Synthetic Organic Chemicals

    Noncompliance period start January 1, 2026 · period end March 31, 2026 · first reported June 30, 2026 · EPA return-to-compliance field March 31, 2026

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    136May 18, 2026InformalState Formal Notice of Violation issued
    137May 18, 2026InformalState Public Notification requested
  3. Monitoring or reporting · Archived

    Monitoring, RegularViolation 178 · 1,2-DIBROMO-3-CHLOROPROPANE · Synthetic Organic Chemicals

    Noncompliance period start January 1, 2026 · period end March 31, 2026 · first reported June 30, 2026 · EPA return-to-compliance field March 31, 2026

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    136May 18, 2026InformalState Formal Notice of Violation issued
    137May 18, 2026InformalState Public Notification requested
  4. Monitoring or reporting · Archived

    Monitoring, RegularViolation 172 · ETHYLENE DIBROMIDE · Synthetic Organic Chemicals

    Noncompliance period start July 1, 2025 · period end September 30, 2025 · first reported December 23, 2025 · EPA return-to-compliance field September 30, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    127November 19, 2025InformalState Formal Notice of Violation issued
    128November 19, 2025InformalState Public Notification requested
  5. Monitoring or reporting · Archived

    Monitoring, RegularViolation 171 · 1,2-DIBROMO-3-CHLOROPROPANE · Synthetic Organic Chemicals

    Noncompliance period start July 1, 2025 · period end September 30, 2025 · first reported December 23, 2025 · EPA return-to-compliance field September 30, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    127November 19, 2025InformalState Formal Notice of Violation issued
    128November 19, 2025InformalState Public Notification requested
  6. Other or unclassified · Resolved

    Consumer Confidence Report Complete Failure to ReportViolation 170 · Consumer Confidence Rule · Consumer Confidence Rule

    Noncompliance period start July 1, 2025 · period end July 22, 2025 · first reported December 23, 2025 · EPA return-to-compliance field July 22, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    126July 22, 2025ResolvingState Compliance achieved
    125September 25, 2025InformalState Formal Notice of Violation issued
  7. Monitoring or reporting · Unaddressed by formal action

    Follow-up Or Routine LCR Tap M/RViolation 166 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start July 1, 2025 · first reported December 23, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    118August 19, 2025InformalState Formal Notice of Violation issued
    119August 19, 2025InformalState Public Notification requested
  8. Monitoring or reporting · Archived

    Monitoring, RegularViolation 168 · ETHYLENE DIBROMIDE · Synthetic Organic Chemicals

    Noncompliance period start April 1, 2025 · period end June 30, 2025 · first reported September 29, 2025 · EPA return-to-compliance field June 30, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    121September 3, 2025InformalState Formal Notice of Violation issued
    122September 3, 2025InformalState Public Notification requested
  9. Monitoring or reporting · Archived

    Monitoring, RegularViolation 167 · 1,2-DIBROMO-3-CHLOROPROPANE · Synthetic Organic Chemicals

    Noncompliance period start April 1, 2025 · period end June 30, 2025 · first reported September 29, 2025 · EPA return-to-compliance field June 30, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    121September 3, 2025InformalState Formal Notice of Violation issued
    122September 3, 2025InformalState Public Notification requested
  10. Other or unclassified · Resolved

    Public Notification Violation for NPDWR ViolationViolation 164 · Public Notice · Public Notice Rule and Revised PN Rule

    Noncompliance period start November 9, 2024 · period end May 15, 2025 · first reported March 31, 2025 · EPA return-to-compliance field May 15, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    110March 26, 2025InformalState Formal Notice of Violation issued
    114May 15, 2025ResolvingState Compliance achieved
  11. Monitoring or reporting · Unaddressed by formal action

    Follow-up Or Routine LCR Tap M/RViolation 163 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start October 1, 2024 · first reported March 31, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    108January 28, 2025InformalState Formal Notice of Violation issued
    109January 28, 2025InformalState Public Notification requested
  12. EPA health-based flag · Resolved

    Treatment Technique, Level 1 Assessment (RTCR)Violation 159 · Revised Total Coliform Rule · Revised Total Coliform Rule

    Noncompliance period start August 17, 2024 · period end April 10, 2025 · first reported February 14, 2025 · EPA return-to-compliance field April 10, 2025

    4 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    103October 9, 2024InformalState Formal Notice of Violation issued
    104October 9, 2024InformalState Public Notification requested
    112April 10, 2025ResolvingState Compliance achieved
    115June 3, 2025InformalState Public Notification received
  13. Monitoring or reporting · Resolved

    Monitoring, Source Water (GWR)Violation 158 · E. COLI · Ground Water Rule

    Noncompliance period start July 17, 2024 · period end August 20, 2025 · first reported February 14, 2025 · EPA return-to-compliance field August 20, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    100September 19, 2024InformalState Formal Notice of Violation issued
    120August 20, 2025ResolvingState Compliance achieved
  14. Other or unclassified · Resolved

    Consumer Confidence Report Complete Failure to ReportViolation 157 · Consumer Confidence Rule · Consumer Confidence Rule

    Noncompliance period start July 1, 2024 · period end August 2, 2024 · first reported February 14, 2025 · EPA return-to-compliance field August 2, 2024

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    102August 2, 2024ResolvingState Compliance achieved
    99September 12, 2024InformalState Formal Notice of Violation issued
  15. Monitoring or reporting · Resolved

    Monitoring and Reporting (DBP)Violation 156 · Chlorine · Stage 1 Disinfectants and Disinfection Byproducts Rule

    Noncompliance period start April 1, 2024 · period end June 30, 2024 · first reported September 19, 2024 · EPA return-to-compliance field June 30, 2024

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    97August 6, 2024InformalState Formal Notice of Violation issued
    113September 3, 2024ResolvingState Compliance achieved
  16. Other or unclassified · Resolved

    Sample Siting Plan Errors (RTCR)Violation 165 · Revised Total Coliform Rule · Revised Total Coliform Rule

    Noncompliance period start December 13, 2023 · period end August 15, 2025 · first reported June 30, 2025 · EPA return-to-compliance field August 15, 2025

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    111April 8, 2025InformalState Formal Notice of Violation issued
    117August 15, 2025ResolvingState Compliance achieved
  17. Monitoring or reporting · Resolved

    Lead Consumer NoticeViolation 135 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start March 31, 2020 · period end April 23, 2021 · first reported June 22, 2020 · EPA return-to-compliance field April 23, 2021

    2 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    58May 8, 2020InformalState Formal Notice of Violation issued
    85April 23, 2021ResolvingState Compliance achieved
  18. Monitoring or reporting · Resolved

    Monitoring and Reporting (DBP)Violation 147 · TTHM · Stage 2 Disinfectants and Disinfection Byproducts Rule

    Noncompliance period start January 1, 2020 · period end December 31, 2020 · first reported April 13, 2021 · EPA return-to-compliance field December 31, 2020

    3 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    80October 30, 2020InformalState Formal Notice of Violation issued
    81October 30, 2020InformalState Public Notification requested
    116September 15, 2022ResolvingState Compliance achieved
  19. Monitoring or reporting · Resolved

    Follow-up Or Routine LCR Tap M/RViolation 129 · Lead and Copper Rule · Lead and Copper Rule

    Noncompliance period start October 1, 2019 · period end June 21, 2021 · first reported March 19, 2020 · EPA return-to-compliance field June 21, 2021

    3 linked actions
    Enforcement and resolution records linked by EPA
    Action IDDateCategoryEPA action type
    45October 30, 2019InformalState Formal Notice of Violation issued
    46October 30, 2019InformalState Public Notification requested
    89June 21, 2021ResolvingState Compliance achieved

EPA data and scope

How to read the records

The enforcement snapshot is federal fiscal 2026Q3. The EPA archive labels its violation file October 13, 2026. EPA says federal reporting can lag by several months. For current advisories, check your utility or local drinking-water authority.

EPA data dictionary and files · EPA reporting and enforcement FAQ · Find an annual water quality report · How to get the report from your utility